
Template revised April 12, 2018.
COMMISSION
DATE: February 28, 2022
TO: Stephen P. Metruck, Executive Director
FROM: Nick Milos, Manager Corporate Facilities
Rod Jackson, Capital Project Manager
SUBJECT: P69 Underdock Utility Replacement – Irregular Bid (CIP #801102) (Short Form)
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to award and execute a
construction contract to the low bidder for the P69 Underdock Utility Replacement project due
to an irregular bid outcome for the three bids submitted, and to increase the project budget in
the amount of $350,000 to fund the irregular bid outcome.
The amount of this request is $350,000 for a total estimated project cost not to exceed
$3,800,000.
SUMMARY
This request is for authorization to proceed with awarding and executing a construction contract
on an irregular bid as required by Resolution No. 3605 Paragraph 4.2.3.4. Three bids were
received in response to the construction advertisement which qualifies the bids as irregular.
Additionally, the lowest bid came in 10.7% over the engineer’s estimate which also qualifies the
bid as irregular. The bid received was $2,585,864 which is $251,864 over the engineers estimate
of $2,334,000. The additional funds requested in this action will be used to cover the difference
of the bid amount and to ensure funds are available for project contingency.
The recommendation is to accept the low bid. The low bidder (Derian Inc.) is a certified Prime
Contractor, a Women and Minority Business Enterprise (WMBE), and a Disadvantaged Business
Enterprise (DBE). Acceptance of the low bid would exceed the project goal of 10% WMBE
participation.
The project scope has been value engineered during the planning and design process to balance
the underdock utilities needs for daily operation versus the longevity of the systems. Rejecting
this current bid would further delay the needed replacements and upgrades and will incur