Key areas of Project cost increases are attributed to:
• Incomplete designs and consequently underestimated
costs of the temporary relocation of the Credential and
Badging office. Lessons Learned from this experience
have been compiled.
• Varying site conditions encountered during demolition
and abatement activities.
• Project soft costs have risen through delays, responding
to varying site condition contractor inquiries, and
additional WELL certification reviews.
• Increased costs for redesign triggered by COVID-19 social
distancing requirements.