Executive Summary
2
• Commission approved the 2012 Development Agreement and 2016 Ground Lease for
the construction of Des Moines Creek Business Park.
• Permits (Clean Water Act) required the construction of two stormwater facilities (Tract
A and Tract B stormwater retention ponds) to be built concurrent with the adjacent
development phase, for conveyance to the City of Des Moines upon completion and the
City’s acceptance.
• In a prior action (2017) Commission approved the surplus of Tract A and conveyance to
the City of Des Moines.
• Tract B stormwater improvements are complete and have been accepted by the City of
Des Moines. This action requests approval of the surplus and conveyance of Tract B.