
COMMISSION AGENDA – Action Item No. __8b__ Page 2 of 7
Meeting Date: January 4, 2022
Template revised June 27, 2019 (Diversity in Contracting).
Port of Seattle’s electrical shop. Some equipment also require modification to comply with
current codes and standards.
These projects will renew and/or replace existing normal and emergency low voltage electrical
distribution equipment within Concourses B, C, and D and the parking garage at STIA.
This request will authorize design and pre-construction funds for both projects.
JUSTIFICATION
Due to the age and conditions of some electrical equipment in use throughout STIA, risk of failure
is moderate to high. A failure of electrical equipment can result in power outages in key areas of
STIA with downstream users such as tenants and travelers being significantly affected for
extended periods of time. As part of the planning phase of these projects, all existing electrical
equipment was surveyed and panels with the highest risk of failure and resulting operational
impact were identified as needing replacement.
Many of the current electrical rooms are cramped and do not have space for new panels or
conduit, and some of the existing panels have clearance issues which impact maintenance access.
As a result, this project must install new electrical rooms and closets to support future electrical
power needs at STIA.
Existing panels are not consistently metered and labeled, particularly for older equipment. This
project will implement metering for all replaced panels, which will provide opportunities for
future energy conservation projects.
C800901 will be implemented in the parking garage and will mostly address lighting panels, many
of which can be replaced during daylight hours. C801280 will be implemented in the concourses,
which represents additional challenges with mitigation of operational impacts, night outages,
and panel relocations. Other than these differences, CIPs C801280 and C800901 will address the
same equipment issues and will include similar design scope. Due to the similarities in the mission
and scope of these projects, implementation with a consistent approach will result in more
efficient procurement, design, and overall project management. As such, projects C801280 and
C800901 are being presented together for this Commission request.
The requested authorization will initiate design activities for both projects and begin pre-
construction activities such as circuit tracing and outage planning to support the design effort.
Diversity in Contracting
The Port of Seattle’s Diversity in Contracting Department performed a Women & Minority
Business Enterprises (WMBE) availability analysis during the Notebook phase of these projects.
Per this evaluation, an aspirational goal of 13% WMBE participation was determined for the
design procurement of both projects (C801280 and C800901), and an aspirational goal of 10%
WMBE participation was determined for the procurement of a GCCM for CIP C801280.