COMMISSION
DATE: March 17, 2021
TO: Stephen P. Metruck, Executive Director
FROM: Melinda Miller, Director, Portfolio and Asset Management
Fred Chou, Capital Program Leader, Seaport Project Management
SUBJECT: Fishermen’s Terminal ADA Compliance Project Design Funding Request
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to proceed with the design
development and permitting phase of the Fishermen’s Terminal ADA Compliance Project (CIP
No. C801198) in the amount of $215,000.
EXECUTIVE SUMMARY
The Port of Seattle entered into a settlement agreement on October 6, 2020, to address
Americans with Disabilities Act (ADA) related deficiencies at the Fishermen’s Terminal parking
lot area south of the Fishermen’s Center Building. The required minor or non-structural
alterations improvements relating to the number of accessible spaces and routes, and the
height and visibility of signage, were completed within 120 days of the effective agreement
date by Marine Maintenance through 2020 expense funds. Other required alterations such as
regrading, filling, demolition, reconstruction or other significant remediation to address
remaining ADA-related issues need to be completed by October 5, 2022. This request would
allow staff to proceed with the design development and permitting phase of the project.
During design development, the project team will continue to coordinate with Fishermen’s
Terminal Site Improvement and Asphalt Paving Project teams to further explore collaboration
opportunities for an integrated approach to the upcoming work. Staff plans on returning to the
Commission to seek construction funding early 2022 upon completion of the design and receipt
of permit approvals.
JUSTIFICATION
This project would help improve safety and maintain Port assets to support the Port’s Century
Agenda objectives under the following strategies:
• Position the Puget Sound region as a premier international logistics hub.