Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No.
8f
ACTION ITEM
Date of Meeting
April 13, 2021
DATE: March 5, 2021
TO: Stephen P. Metruck, Executive Director
FROM: Wayne Grotheer, Director, Aviation Project Management
Wendy Reiter, Director, Aviation Security
SUBJECT: North Satellite Transit System (STS) Employee Screening Design, Equipment
Purchase and Construction Authorization (CIP #C801153)
Amount of this request:
$1,400,000
Total estimated project cost:
$1,400,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to (1) complete design, (2) execute
contracts for screening equipment, and (3) use Port crews and small works contracts for
construction in support of the North Satellite Transit System Employee Screening project at
Seattle-Tacoma International Airport, in the amount of $1,400,000.
EXECUTIVE SUMMARY
The North STS Employee Screening project will design and construct a new employee screening
location within the North Satellite Transit System (STS) station at the main terminal, allowing for
greater airport security and safety improvements for personnel arriving to work each day. This
project further enables the Port commitment made toward 100% employee screening by
replacing the existing central employee screening location with one that has space for advanced
screening technology. The project will improve safety by no longer requiring screened airport
personnel to walk through locations in the congested bagwell after screening.
JUSTIFICATION
This project supports the Port of Seattle goal of achieving 100% employee screening at Seattle-
Tacoma International Airport (SEA). Currently, many employees are entering the secure side of
the airport through employee portals and employee screening checkpoints; however, the
equipment being used is not federally certified. The existing central screening location does not
provide the area needed to house the Transportation Security Administration (TSA) certified
equipment that the security department requires. The Baggage Optimization project will be
closing the existing pedestrian pathway in the bagwell outside of the Central Employee Screening
COMMISSION AGENDA Action Item No. _8f_ Page 2 of 5
Meeting Date: April 13, 2021
Template revised June 27, 2019 (Diversity in Contracting).
Checkpoint, this will prevent Northbound airport staff from reaching their daily work
assignments without undue travel routes. This project will facilitate the continued screening of
employees at the STS level of the main terminal, while increasing the level of safety for both
pedestrians and tug operators in the bagwell by limiting foot traffic. The Airline Realignment and
Checkpoint One relocation projects require the existing central screening location to be vacated
in order to repurpose the space to a planned United Airlines baggage service office (BSO). The
addition of a screening position in the North STS will enable the airport to add security assets to
the space and allow for better overall security. The project will also install infrastructure in
support of this project which will increase the overall value of the space.
Diversity in Contracting
In partnership with the Diversity in Contracting department in outreach, this project will be
performed by Port Construction Services (PCS) and will utilize small works contracts that typically
utilize women and minority owned business enterprises (WMBE) as primes.
DETAILS
The project will relocate central employee screening to the North STS and improve safety and
security for the airport. The project budget requested is $1.4 Million. The project will be designed
utilizing an existing Indefinite Delivery Indefinite Quantity (IDIQ) architectural firm. Capacity for
this design has been reserved in anticipation of approval. The project will utilize PCS and Aviation
Maintenance (AVM) resources to complete the installation of the equipment. The project has an
approved sole source competition waiver, which will be used to procure an Advanced Imaging
Technology (AIT) screening machine valued at approximately $385,000. The AIT is compliant with
the American with Disabilities Act (ADA), will allow screening for all personnel without need for
any additional accommodation, is TSA certified and complies with current federal guidelines. The
equipment will have a recurring maintenance contract, which will be budgeted within the
Aviation Security department’s annual operating budget.
Scope of Work
The project will include the following key components:
(1) Installation of glass and drywall partition walls to establish a perimeter for the new
screening location;
(2) Equipment such as AIT screening machine, network demark cabinets, electrical
distribution panel, LED lighting, cameras, and access controls;
(3) Infrastructure that supports the equipment;
(4) Relocates existing central screening x-ray equipment and casework; and
(5) Selection of exterior finishes will take into consideration that it is in a public facing and
high traffic location.
COMMISSION AGENDA Action Item No. _8f_ Page 3 of 5
Meeting Date: April 13, 2021
Template revised June 27, 2019 (Diversity in Contracting).
Schedule
Activity
Design start
Construction start
In-use date
Cost Breakdown
This Request
Total Project
Design
$160,000
$160,000
Construction
$825,000
$825,000
Total
$1,400,000
$1,400,000
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1Do nothing.
Cost Implications: $0
Pros:
(1) No additional expenditure.
(2) No impact to security operations.
Cons:
(1) The equipment used would not be compliant with current federal TSA guidance.
(2) The safety of employees would remain unimproved.
(3) Airport personnel would be impacted by pedestrian tunnel closure as a result of the
Baggage Optimization project, this would increase their foot travel significantly.
(4) The Airline Realignment and Checkpoint One relocation projects would need to
establish a new location for the planned baggage service office relocation.
This is not the recommended alternative.
Alternative 2 Relocate the screening position without the new AIT equipment utilizing only
existing equipment.
Cost Implications: $1M
Pros:
(1) This improves employee safety reducing foot traffic in the bagwell operational space.
(2) Cost savings associated with procurement of the new equipment.
(3) No additional training for equipment operations necessary.
(4) This mitigates the impact of the Baggage Optimization pedestrian tunnel closure.
(5) This allows the former central position to be reallocated enabling the Airline
Realignment and Checkpoint One projects to utilize the space for a future BSO.
Cons:
(1) The screening room would not be compliant with current federal TSA guidelines which
could lead to future regulatory issues with the program.
COMMISSION AGENDA Action Item No. _8f_ Page 4 of 5
Meeting Date: April 13, 2021
Template revised June 27, 2019 (Diversity in Contracting).
(2) The screening room would not be compliant with ADA guidelines and would necessitate
additional accommodation for employees with special needs.
(3) Additional foot traffic in the North STS.
This is not the recommended alternative.
Alternative 3Perform the project as proposed with the new AIT equipment.
Cost Implications: $1.4M
Pros:
(1) This improves employee safety reducing foot traffic in the bagwell operational space.
(2) This provides a federally compliant screening location meeting TSA standards.
(3) This provides an ADA compliant screening process.
(4) This mitigates the impact of the Baggage Optimization pedestrian tunnel closure.
(5) This allows the former central position to be reallocated enabling the Airline
Realignment and Checkpoint One projects to utilize the space for a future BSO.
Cons:
(1) Additional foot traffic in the North STS.
(2) Training of equipment operators will be required.
This is the recommended alternative.
FINANCIAL IMPLICATIONS
Cost Estimate/Authorization Summary
Capital
Total
COST ESTIMATE
Original estimate
$2,100,000
$2,100,000
Previous changes net
($700,000)
($700,000)
Revised Estimate
$1,400,000
$1,400,000
Art (Transfer to Art CIP)
($14,000)
($14,000)
Revised Total
$1,386,000
$1,386,000
AUTHORIZATION
Previous authorizations
$0
$0
Current request for authorization
$1,400,000
$1,400,000
Total authorizations, including this request
$1,400,000
$1,400,000
Remaining amount to be authorized
$0
$0
COMMISSION AGENDA Action Item No. _8f_ Page 5 of 5
Meeting Date: April 13, 2021
Template revised June 27, 2019 (Diversity in Contracting).
Annual Budget Status and Source of Funds
This project, CIP C801153, was included in the 2021-2025 capital budget and plan of finance with
a budget of $2,100,000. A budget decrease of $700,000 was transferred from the Aeronautical
Reserve CIP (C800753) and $14,000 to the Art Pool C102066 resulting in zero net change to the
Aviation capital budget. The funding source will be the Airport Development Fund (ADF).
Financial Analysis and Summary
Project cost for analysis
$1,400,000
Business Unit (BU)
Terminal Building
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase due to inclusion of
capital (and operating) costs in airline rate base.
IRR/NPV (if relevant)
N/A
CPE Impact
Less than $.01 in 2022
Future Revenues and Expenses (Total cost of ownership)
Funding for the maintenance and training contract will be included in the Aviation Division
operating budget and approved through the 2022 Aviation Division expense budget approval
process.
ADDITIONAL BACKGROUND
None.
ATTACHMENTS TO THIS REQUEST
(1) PowerPoint Slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
None.