
Central Terminal Infrastructure Upgrade Project
Executive Summary
Internal Audit (IA) completed an audit of the Central Terminal Infrastructure Upgrade Project (Project)
for the period October 2014 through November 2020. The audit was performed to assess the quality
of the Port’s monitoring of the Project to assure it was meeting project management standards in an
efficient and effective manner.
The Project will be audited in two parts; this audit focused on the bidding and design phases while the
second audit will focus on the construction and closeout phases, which is scheduled to occur in the
1
st
quarter of 2021.
The delivery method for this Project was a design-bid-build with a lump sum contract. The Port
entered into an agreement with HNTB Corporation (HNTB) on October 23, 2014 to furnish design
services for the Terminal Utility Upgrades Design of Airport Dining and Retail project. In 2016, the
Airport, Dining and Retail Infrastructure Modifications project and the Central Terminal HVAC
Upgrade project were advertised, but due to incoming bids being higher than the engineer’s estimate,
both procurements were canceled in October 2016. As a result of these irregular bids, the project
management team combined the two construction projects into one larger project and estimated the
combined Project to be $10.2 million. Osborne Construction Co. (Osborne) was awarded the contract
in the amount of $9.3 million.
The contract required that the contractor substantially complete the work no later than 730 days
following the contract execution date, which would have been December 26, 2019. Based on the
October 2020 trend log, there have been an additional 278 approved days that have extended
substantial completion to September 29, 2020. As of the conclusion of this audit, the Contractor had
not completed the Project. Currently, the Port’s project team stated that the Project will be
substantially completed at the end of November 2020.
Through discussions with the Port’s project staff, one of the main reasons that the project did not
meet critical milestones, and experienced cost overruns, was the lack of involvement from key
stakeholders during the review and approval of designs. Additional reasons that contributed to project
delays and cost overruns, included the lack of design review after merging the two original projects,
and Port turnover in key departments involved with the Project. Management conducted a “lessons
learned” assessment for the Project in 2019, in which they self-identified these issues.
The construction contract total is currently $12.2 million, which includes approximately $2.7 million in
change orders (COs); a 29% increase in project costs. Although not all change orders could have
been prevented during the design phase, a stronger design and approval process could have
prevented some of them. Additionally, we have noted similar concerns in other audits of capital
projects. We identified the following opportunity where internal controls need to be enhanced or
developed. This opportunity is discussed in more detail beginning on page seven of this report.
1. (Medium) The lack of involvement, participation, and collaboration between the key stakeholders
during the review and approval of designs resulted in additional project costs and schedule
delays.
Glenn Fernandes, CPA
Director, Internal Audit