COMMISSION AGENDA – 8c Page 2 of 5
Meeting Date: November 10, 2020
Template revised September 22, 2016; format updates October 19, 2016.
to new supports along the Concourse C building. Removing and relocating these 400Hz conduits
will allow replacement of the C9 PLB without shutting down the 400 Hz power for an extended
period of time to 8 other operating gates and significantly affecting airline operations.
Background
The proposed pathway of the relocated conduits shares the same working space as the
Concourse C Power New Center project currently under construction. The PLB project schedule
overlaps with the Concourse C Power Center and both projects are in the same physical
workspace with significantly increase risks to both projects. To avoid multiple contractors
working in the same space and reduce or eliminate the risk of increased cost and time impacts
for both projects, the best alternative is to perform the work as a change order to the Concourse
C New Power Center project.
The PLBs at Sea-Tac Airport have a high utilization in comparison to airports with comparable
annual enplanements. In 2019, Sea-Tac Airport processed approximately 336,000 passengers per
bridge, well above the average of the top 20 airports of approximately 220,000 passengers. The
PLBs that are being replaced are at, or near, their end of life. Any unplanned downtime due to
PLB or fixed walkway failure impacts airlines and customer service.
Gate C9 is one of the two bridges that will be replaced in 2021. The Gate C9 bridge has the
additional difficultly that the power lines to the 400 hz generators, and the resulting distribution
lines to eight (8) other Concourse C gates, run along the fixed walkway section of the Gate C9
PLB. In order to safely replace the fixed walkway section, the cables and conduits need to be
removed and rerouted; after which, the conduits and cables can be reconnected. This method
would leave eight (8) gates without gate 400 hz power for approximately 3 to 4 months while the
bridge is replaced and reconnected. Relocating the 400 hz in advance will avoid airlines having to
run their engines or operate diesel generators to maintain 400 hz supply at the other 7 gates
while the gate C9 bridge is replaced. This relocation work must be completed by June 30, 2021,
to prevent overlap with the PLB bridge replacement project.
FINANCIAL IMPLICATIONS
There is no additional funding being requested in this memo. Previously authorized funding will
be transferred from CIP #C800793 to CIP #C800724.