COMMISSION AGENDA – Action Item No. __6e__ Page 2 of 4
Meeting Date: October 27, 2020
Template revised June 27, 2019 (Diversity in Contracting).
Diversity in Contracting
The project staff discussed the project with the Diversity in Contracting (DC) department, and
both project staff and the DC department decided that it is not feasible to subcontract on this
project. Thus, the project will not have a woman and minority business enterprise (WMBE)
aspirational goal. The project staff will continue to work with the DC department on outreach to
determine if the work can be performed by a WMBE prime contractor.
DETAILS
The Port of Seattle currently utilizes two 1500 kW emergency generators to supply NFPA/
National Electrical Code (NEC) required emergency power to Concourses B, C, D, the Central
Terminal, and the South Satellite. These emergency generators are located at the Loading Dock
level of the SEA Airport Main Terminal building and are approximately 20 years old.
The control and operation of these generators is through a set of microprocessor-based
programmable logic controllers that have been discontinued and are no longer supported by the
manufacturer. This project will replace and upgrade the existing control system and thereby
extend the useful life of the generator sets, valued at $10 million, by an estimated 20 years.
This system provides code-required emergency power. The Washington Administrative Code
(WAC) 296-46B-700 states all exit and emergency lights must be installed in accordance with
Article 700 of the NEC. Emergency systems may also provide power for such functions where
interruption would produce life safety hazards. During construction staff will be on standby to
manually engage emergency power if necessary.
Scope of Work
This project will replace and program new programmable logic controllers (PLCs) for the
emergency generator control system, for the two 1500kW generators in the generator control
room. Controller installation and related work shall be accomplished in the generator control
room, near the central terminal loading dock. The existing Generator Ancillary Systems Control
Panel shall have the existing PLC upgraded with a new PLC due to space constraints. Electrical
installation work will occur in the generator room, generator control room, PLC cabinets, and
other locations necessary to route power testing. The existing Direct Digital Controls panel
located at the entry way into the generator room will be upgraded with a direct replacement.
Schedule
Activity