COMMISSION AGENDA – Action Item No. _6h___ Page 2 of 6
Meeting Date: October 13, 2020
Template revised June 27, 2019 (Diversity in Contracting).
systems to current code. In addition, this project will include full asbestos removal from the
ceiling.
Staff will return to the Commission following the completion of the preliminary design work. At
this time staff will provide an updated project cost estimate and request authorization to move
forward with the next phase of project delivery. Staff will also request authority to add significant
money into the design contract amending it to authorize the design team to complete full design
and be available to provide design support during construction.
JUSTIFICATION
For the Main Terminal building to meet current code, the entire building must have a sprinkler
system installed. This will involve removing the existing ceiling, abating asbestos in the area, and
putting in new ceiling and lighting on ticketing, baggage claim, and the skybridge level. New
lighting controls to improve efficiency will also be included.
In addition to sprinklers, a fully-integrated smoke control system will need to be installed. The
smoke control system will include adding exhaust fans and connecting to an upgraded emergency
power system. The existing emergency power is not sufficient to meet the demand of the new
smoke control system and will require significant upgrades.
The existing emergency power system supports the Main Terminal; Concourses B, C, and D; and
the South Satellite. The total future emergency power need of these spaces is currently unknown.
Therefore, the preliminary design will focus on designing the smoke control system for all areas
except the South Satellite and evaluate any other code-required emergency power needs to
determine the total system requirement. The South Satellite will get its own dedicated
emergency power and smoke control systems when it is renovated. The future C1 building will
also be incorporated into the total emergency power needs.
All of this must be completed in a facility that is operational 24 hours a day, every day of the year.
Although currently passenger traffic is reduced, it is anticipated that traffic numbers will have
returned to 2019 levels by the time of construction and the project will need to be able to limit
impacts when that occurs. This is a complex project and the preliminary design is an important
first step to help mitigate some of the unknown risks to be able to provide a better cost estimate
and schedule. As part of the preliminary design we will conduct an operational impact analysis.
In addition to the design of smoke control and emergency power, the preliminary design will
include an updated cost estimate. The $4,500,000 not-to-exceed amount represents 50% above
the initial estimate, that is $3,000,000 for the preliminary design. Full design is estimated at
$40,000,000.
Project Scope and Budget Controls