Original Budget: $ 8,819,590
Revised Budget: $13,500,000
Budget increase due to:
• Scope Changes (additional traffic
signals, Cell Phone Lot
improvements, landscaping,
unknown site conditions, sewer
capacity improvements)
• Consultant vs. Staff Support
• Cost escalation
Original Completion: 2020 Q3
Revised Completion: 2021 Q3
Schedule delay due to:
• Late external review responses
• Protracted consultant rate
negotiations
• Resource constraints
Project Budget and Schedule