DATE: October 5, 2020
TO: Stephen P. Metruck, Executive Director
FROM: Stephanie Jones Stebbins, Managing Director, Maritime Division
Arthur Kim, Project Manager, Marine Maintenance
Catherine Chu, Capital Project Manager, Seaport Project Management
SUBJECT: Authorization for Construction of Bulkhead Stabilization Project at Terminal 30
(CIP # 801155)
ACTION REQUESTED
Request Commission authorization for the Executive Director to advertise and execute
construction contracts for the Terminal 30 (T-30) Bulkhead Stabilization Project for an estimated
amount of $802,000 additional funding with the total project authorization of $1,100,000.
EXECUTIVE SUMMARY
The existing bulkhead, or seawall, at the north end of T-30 is estimated to be over 70 years old
and a section of it is failing. If left alone, the entire wall is at risk of failure, causing erosion of
upland soil into the East Waterway. In order to preserve the asset and protect the environment,
the recommended remedy is to: a) patch up the bulkhead to prevent trapping fish in the affected
area and prevent further erosion, and b) excavate behind the bulkhead and replace it with riprap
to stabilize the remaining bulkhead and preserve land. This will stabilize the area for the
foreseeable future, while leaving options open in the long- term for the Port to either replace the
entire wall or remove the wall and regrade the land behind the wall.
Total estimated project cost is $1,100,000, including approximately $80,000 costs to date for
design. If authorized by the Commission, construction is planned to start in late 2020, and to be
completed by summer of 2021.
JUSTIFICATION
The purpose of the project is to preserve the asset and protect the environment. With no action,
the damage to the bulkhead and erosion will continue in the immediate future. In the medium
to long-term future, the entire bulkhead is expected to fail without intervention.