AOA Perimeter Fence Line Standards Project
Schedule of Findings and Recommendations
The Contractor’s lack of experience with the Port’s contract provisions and inadequate
management of the Project resulted in critical milestones not being met, negatively impacting
the completion dates.
The Project was awarded to Massana Inc. on February 26, 2019 and a Notice to Proceed was issued
on April 12, 2019. The initial duration of the contract was for 225 calendar days. The Contract’s terms
required Substantial Completion by October 9, 2019. Physical Completion was to occur 120 days after
Substantial Completion.
Events such as; Covid-19 impacts, adverse weather in December 2019 and January 2020, lack of
information in the contract documents, and Port design errors and scope changes resulted in the
Port’s approval of 181 additional days through change orders. With these additional days, Substantial
Completion was extended to April 7, 2020 and Physical Completion to November 29, 2020.
Besides the approved reasons for the extension to the completion of the Project, the Contractor’s lack
of timely development of fall protection compliance documents, lack of experience with the Port’s
contract provisions, failure to provide adequate resources, and inadequate managing of the Project,
resulted in the Substantial Completion milestone not being met. Additionally, there is a possibility that
the Physical Completion milestone will also be missed.
On February 25, 2020, The Port issued a Notice of Forbearance, that the Port was willing to forbear
taking action to impose Liquidated Damages for 90 days from the date of the letter. According to the
letter, the Contractor was expected to meet certain criteria, including: completion of the project within
the 90 days, submitting information justifying the delay, and providing time for the Port to complete its
analysis of the matter. The letter stated that if the Contractor did not meet the criteria, the Port
reserved the right to assess Liquidated Damages from the original milestone date. The Contractor did
not meet the requirements of the letter.
The Contract allows the Port to pursue liquidated damages of $1,207 per day after the Substantial
Completion date and, starting 60 days after Substantial Completion, $323 per day until Physical
Completion is met. The Port anticipates that Substantial Completion will not be achieved until the end
of September 2020. Based on a projected five-month delay, we estimate that the Port will be entitled
to pursue approximately $232,000 in liquidated damages, however, the final amount is unknown until
the Project is complete and a full reconciliation is performed.
Recommendation:
Upon completion of Project, Port management should calculate and pursue liquidated damages from
the Contractor.
Management Response/Action Plan:
The team agrees with the recommendation that Liquidated Damages should be imposed in the
amount of $1,207 per day for unexcused delays beyond the original Substantial Completion date and
$323 per day for unexcused delay beyond the Physical Completion date. The team fully intends to
pursue Liquidated Damages and that has been conveyed to the Contractor. Liquidated Damages will
be assessed once the Contractor achieves Substantial and Physical Completion when we can quantify
the actual unexcused delay.
DUE DATE: December 31, 2020