PORT COMMISSION MEETING MINUTES Page 2 of 8
TUESDAY, JULY 28, 2020
Minutes of July 28, 2020, submitted for review on August 6, 2020, and proposed for approval on August 11, 2020.
• Ms. Laureen France, Citizen, submitted written materials regarding impacts to the
environment from aviation and cruise ships, which are attached as minutes Exhibit B;
• Ms. Laura Gibbons, Citizen and volunteer member of 350 Seattle’s Aviation Team,
submitted written materials regarding sustainable air travel and reducing aviation, which
are attached as minutes Exhibit C;
• Ms. Beredine Lund, Member of 350 Seattle, submitted written materials regarding Item 8a,
sustainable air travel, and climate change, which are attached as minutes Exhibit D;
• Ms. Mary Lou Pauly, Mayor of Issaquah, submitted written materials regarding the City’s
support of the Port’s economic development partnership program, which are attached as
minutes Exhibit E;
• Mr. Samson Seged, Citizen, submitted written comments regarding airport taxi fares and
current trip reductions, which are attached as minutes Exhibit F;
• Mr. Sarah Shifley, Member of 350 Seattle’s Aviation Team, submitted written comments
regarding Item 8a and lower carbon travel, which are attached as minutes Exhibit G; and
• Ms. Charlotte Wells, of Port Townsend, submitted written comments asking for reduction
of flights at SeaTac airport, which are attached as minutes Exhibit H.
6. UNANIMOUS CONSENT CALENDAR
[Clerk’s Note: Items on the Unanimous Consent Calendar are not individually discussed.
Commissioners may remove items for separate discussion and vote when approving the agenda.]
6a. Approval of the minutes of the June 30, 2020, special meeting.
6b. Authorization for the Executive Director to execute a five-year Interlocal Agreement (ILA)
with the Washington Public Ports Association, Port of Anacortes, Port of Bellingham,
Port of Everett, Port of Kalama, Port of Longview, Port of Olympia, Port of Port Angeles,
Port of Tacoma, and Port of Vancouver USA (each a “Port” and collectively, “the Ports”)
in a form substantially similar to what is attached, with only minor changes approved by
counsel for the Port of Seattle. The ILA will require a five-year commitment of up to a
total of $300,000, funded annually through the Port’s capital program. No funding is
being requested at this time.
Request document(s) included an agenda memorandum, presentation slides, and an agreement.
6c. [Removed from agenda prior to publication.]
6d. Authorization for the Executive Director to advertise and award a major public works
contract for replacement of 1,270 feet of fender system at Terminal 91 in the amount of
$7,650,000 of a total project cost of $8,500,000. (CIP #C801097)
Request document(s) included an agenda memorandum and presentation slides.
6e. Authorization for the Executive Director to advertise and execute a major works
construction contract for the second phase of the Parking Garage Elevator
Modernization Project at Seattle-Tacoma International Airport. The amount of this
request is $16,160,000 for a total estimated project cost of $23,276,000. (CIP #C800789)