COMMISSION AGENDA – Action Item No. _8b___ Page 2 of 8
Meeting Date: July 28, 2020
Template revised June 27, 2019 (Diversity in Contracting).
The EGSE charging infrastructure project is being executed in three major phases (Phase 1,
Phase 2A, and 2B). Phase 1 (north-end) has been completed, and this request will fund the
completion of Phase 2 (south-end). The second phase of the project has incurred a seven-year
delay due to airline realignment, major projects construction, and increased duration for Airline
transition to electrified vehicles. Following an evaluation of the south satellite, the scope at that
location, which included 72 charge ports and a new power center, was removed from this EGSE
project; however, 8 charge ports will be installed at the south satellite under phase 2B.
The current approved budget is $30,700,000. The revised budget is estimated to be
$38,100,000. The budget increase of $7,400,000 is due to escalation of labor and materials
costs since the original estimate was developed eight years ago, added scope for arc flash
mitigation, design updates, an increased number of construction packages, and contractor
markup on chargers.
BACKGROUND
This project will help complete the vision championed by airlines and the Commission in 2010
to be the first North American airport to offer electric charging infrastructure to all operators.
Most airports have implemented electrification on an airline-by-airline basis, whereas this
project creates a harmonious system for use by all airlines.
The project will reduce carbon and criteria pollutant emissions from ground support
equipment, reduce airline maintenance costs, save fuel costs, and contribute to the Century
Agenda goal to “Be the greenest and most energy efficient Port in North America.”
The initial project development in 2012 proposed 512 charge ports airport-wide. Phase 1
included 256 charge ports, which was completed in 2014, with support from a U.S. Department
of Energy grant. In 2014, Alaska Airlines deployed 204 electric-powered baggage tractors and
baggage belt loaders for use at their Alaska and Horizon gates. Southwest, United and Delta
also began using limited numbers of EGSE in 2015, given the growing positive response from
the airlines about the operational benefits of using electric equipment.
In 2015-17, before Phase 2 could be implemented, several new construction projects came on-
line, including D Concourse Holdroom, North Satellite renovations, and the International
Arrivals Facility. This new complexity and changes to the apron and gates led to a delay in EGSE
installations. Phase 2A and 2B will complete the majority of the originally planned EGSE charge
points in this new, re-configured environment.
Following an evaluation of the south satellite, the scope at that location, which included 72
charge ports and a new power center, was removed from this EGSE project. The construction
budget for this south satellite scope was $3.2M. This remaining EGSE South Satellite (SSAT)
buildout will be addressed in the future renovations of the SSAT, thus avoiding costly rework if
installed now. The current EGSE project scope includes eight charge ports at the SSAT. The