DATE: July 20, 2020
TO: Stephen P. Metruck, Executive Director
FROM: Laurel Dunphy, Director, Aviation Operations
Wayne Grotheer, Director, Aviation Project Management Group
SUBJECT: Parking Garage Elevator Modernization (CIP# C800789)
ACTION REQUESTED
Request Commission Authorization for the Executive Director to advertise and execute a major
works construction contract for the second phase of the Parking Garage Elevator Modernization
Project at Seattle-Tacoma International Airport. The amount of this request is $16,160,000 for a
total estimated project cost of $23,276,000.
EXECUTIVE SUMMARY
The Airport Parking Garage elevators provide vertical circulation services for millions of airport
parking and ground transportation customers every month. Continued and reliable operations
of these systems are vitally important to the traveling public, as well as Airport operations.
The first phase of this project will weatherize the 8th floor Parking Garage Sections B and C
elevator cores, eliminate slip or trip hazards, and improve the customer experience in the
Parking Garage elevator lobbies. The construction contract for this phase of work was recently
executed, and a “notice-to-proceed” will be issued for this work on July 27, 2020. The second
phase of the project replaces worn end-of-life elevator components with modern, energy-
efficient systems in all five elevator cores in the Parking Garage.
JUSTIFICATION
This project provides for continued reliable vertical circulation services within the airport
Parking Garage for the next ten plus years, while reducing repair costs and decreasing energy
consumption. The modernized elevators will use energy efficient regenerative drives that use
less energy and produce less waste heat. The total energy saving estimate is 56,000 to 211,000
kilowatt hours (kWh), per year. While this energy reduction represents just approximately 0.1
percent of the total airport electrical energy consumption, the project will contribute to the
Port’s goal to be the greenest and most energy efficient port in North America. Additionally,
this project will contribute to the Port’s Long-Range Plan to improve customer service.