2020 Airfield Pavement
Program Acceleration
Seattle-Tacoma
International Airport
Item No. 6d supp
Meeting Date: May 12, 2020
Airfield Program Acceleration
Advance airfield pavement and utility improvements currently
scheduled for years 2021-2025 into this years construction
work to capitalize on reduced airfield activity
Reduce future, planned impacts to airlines at “Spot 88” by
completing this work now
This action requires:
Transfer of $2.8M in programmed funds from 2021-2025 Airfield
Program into current 2016-2020 Airfield Program CIP
Authorization to execute a Not-to-Exceed change order of $2.3M
2
2020 Airfield Pavement Project
Program Acceleration Locations
3
“SPOT 88”
2020 Airfield Pavement Project
Failed Channel Drain Fuel Tank Puncture
4
Project Schedule
5
2020 Airfield construction start
April 2020
Acceleration work start
mid
-May 2020
Acceleration work in
-use date
Q3 2020
2020 Airfield construction completion
Q4 2020
Project Budget
2016-2020 Airfield Improvement Program
6
COST ESTIMATE
Capital
Expense
Total
Original estimate
$25,830,000
$0
$25,830,000
Budget transfer (CIP 800930 to CIP 800483)
2,800,000
0
2,800,000
Revised estimate
28,630,000
0
28,630,000
AUTHORIZATION
Previous authorizations
25,830,000
0
25,830,000
Current request for authorization
2,800,000
0
2,800,000
Total authorizations, including this
request
28,630,000
0
28,630,000
Remaining amount to be authorized
$0
$0
$0
Program Acceleration Risks
Worker Safety and COVID-19
Project is underway and has approved COVID-19 safety plan
Work does not require additional contractor staff. Normal project
work is scheduled for spring and fall to avoid summer airfield
impacts. Due to decrease in operations, contractor can keep their
crew on the job, working through the summer
Return of Airfield Activity
Acceleration work is phased with multiple off-ramps to allow “return
to service” of areas if needed by operations
7