COMMISSION AGENDA – Action Item No. __6d__ Page 2 of 7
Meeting Date: May 12, 2020
Template revised June 27, 2019 (Diversity in Contracting).
replacement area; (2) Add utility sleeves underneath the taxilane pavement replacement to
accommodate future planned utility replacements; and (3) Replace a failing channel drain
adjacent to the current pavement replacement area. This failed channel drain recently came
loose and punctured a fuel tank on a fuel truck. These three items are currently programmed and
budgeted as part of the next cycle of airfield pavement and utility replacements. Performing this
additional pavement and utility work now reduces the future impact to airlines at Spot 88 by
completing this work while airport operations are low. Aviation Operations is requesting this
work be accelerated from its current planned replacement window currently scheduled for
between 2021 and 2025.
A Change Order is required to direct the Contractor to proceed with the additional work. This
Change Order will be issued for an amount Not-To-Exceed $2,300,000. This also requires a budget
transfer of $2,800,000 of programmed funds from the 2021-2025 Airfield Pavement and
Infrastructure Program (CIP C800930) to the 2016-2020 Airfield Improvement Program.
Additionally, the base project work is receiving Federal Aviation Administration (FAA) Airport
Improvement Program (AIP) Grant Funding and the project team has requested FAA participation
in the change order work to the maximum extent available through FAA discretionary funding.
JUSTIFICATION
The 2020 Airfield Pavement Replacement Project is the last construction project of the 2016-
2020 Airfield Improvement Program (CIP C800483) and is a continuation of the programmatic
approach of replacing distressed airfield pavement and utilities having exceeded their planned
lifespan. Replacing damaged infrastructure on the airfield maintains the integrity of airfield
pavements and enables continuing airport operations. Deferring damaged pavement and utility
replacement increases risk to airfield operations, damage from Foreign Object Debris (FOD),
increases the likelihood of emergency work, and drives costs higher in the future.
Rapidly deteriorating infrastructure and recent incidents on the airfield (i.e., where a channel
drain grate came loose and punctured a fuel tank) have identified the need to accelerate portions
of work forward to this year. Performing this work now also reduces the future impact to airlines
by completing planned work while airport operations are low. The proposed change order work
is immediately adjacent to, or underneath of, the existing 2020 pavement work and there are
cost efficiencies and savings on escalation to doing the work now.
Planned future disruptions to airfield operations at the Spot 88 taxilane intersection due to
construction will still occur if no action is taken. Also, taking no action will lead to additional
unplanned disruptions and potential future safety incidents resulting from continued failing
infrastructure. Finally, should the utility portion of the work not happen concurrent to the
planned pavement work, there will be added Port cost for having to go back and install utilities
in new pavement.