COMMISSION AGENDA – Action Item No. __6c__ Page 5 of 5
Meeting Date: April 28, 2020
Template revised June 27, 2019 (Diversity in Contracting).
Existing distribution equipment will be re-fed from the new Power Center, thus re-establishing
the Fire Zones. The purpose of the fire zones is to have all electrified equipment within a zone
fed from a single source within that zone. Currently several distribution panels are fed from the
C1 building. This project will remove the feeds from the C1 Power Center and re-route them to
the new Power Center (which will also free up capacity on the C1 power center for the Baggage
Optimization Project and for future C1 building expansion.) This will create a new fire zone for
all power derived from the Concourse C new power center providing a means to readily isolate
all normal electrical power and therefore minimize a hazardous condition for the Fire
Department in the event of a fire in this fire zone.
The existing electrical distribution equipment at the North end of Concourse C is also near rated
capacity and some of the equipment is obsolete. This project will add new distribution
equipment and will replace the obsolete equipment. The obsolete equipment is of concern
because parts are no longer manufactured and if there is a failure with this equipment, we
could face an extended power outage as we scramble to find alternate sources of power for the
equipment and tenants it serves. The new distribution equipment will provide electrical
infrastructure to support new projects at the north end of Concourse C.
The project design phase was extended due to the following.
• The project schedule was originally developed based on an established location for the new
power center on the west side of the concourse. When the project preliminary design was
nearly complete, the project was directed by Aviation Management to move the new power
center to the east side of the concourse. This required significant redesign and delayed the
completion of the project.
• The Port determined standardization of major electrical equipment including programmable
logic controllers, meters, and switchgear was required via an RFP process. Because this
project included all the equipment proposed for the standardization memo, it was
determined the project would benefit from this, therefore the design schedule was delayed
until completion of the RFP process.
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
September 22, 2015 – The Commission authorized $1,900,000 to execute a design contract,
prepare design and construction bid documents, and authorized the use of Port crews
for preliminary work in support of this project.