Project Risks
• Federal Aviation Administration (FAA) Approval of Airport
Layout Plan (ALP) change
– The construction of the new Taxiway Y requires FAA approval for an
ALP change prior to construction start
– A successful Safety Risk Management Panel was conducted with the
FAA for the ALP change and the corresponding FAA approval letter is
expected no later than May 2020
• Inclement weather
– Potential delay to the overall construction progress