Villa Enzian Condominium Sound Insulation
Commission Meeting
March 24, 2020
Item No. 6e
Meeting Date: March 24, 2020
Villa Enzian Condominiums
2
Noise Remedy Boundary
3
Schedule and Budget
4
Design Start
2019 Quarter 4
Construction Start
2020 Quarter 4
Construction Complete
2021 Quarter 3
Villa Enzian
Remaining
Two Complexes
Total
Design
$822,000
$4,285,000
$5,107,000
Construction
$2,438,000
$12,455,000
$14,893,000
Total
Cost
$3,260,000
$16,740,000
$20,000,000
Potential Risks
5
- Inability to obtain FAA Grant Funding after project completion
- Delays due to COVID-19 virus
- Difficulty obtaining qualified staffing resources
- Difficulty attracting qualified contractors in a hot construction market
- Delays in obtaining subordination agreements from lenders
- Uncertain product availability from suppliers
- Challenges with multiple Authorities Having Jurisdiction