COMMISSION AGENDA – Briefing Item No. _9a_ Page 2 of 5
Meeting Date: March 10, 2020
Template revised September 22, 2016.
The project team worked with Airport Operations to ensure a comprehensive Safety Risk
Assessment to assure sufficient space will be available for air carrier movement on and around
the ramp area as well as continued visual observation of the dual taxi lane between Concourse C
and the North Satellite will be maintained.
Further strategies to manage, or alleviate ramp area congestion, in the areas of Concourse C and
D, include a future Centralized Receiving Distribution Center, by way of ensuring there are only
box truck type deliveries to the load dock. Deliveries will still be able to access the building by
way of the central terminal load dock.
The proposed C1 Building Expansion project, will provide solutions to deficient ADR, hold room,
lounge and office capacities by adding four floors to the existing C1 Building, increasing the
existing approximate 99,000 SF facility to roughly 203,000 SF, and expand the adjacent C3 Hold
room by approximately 1,500 square feet.
The Airport currently underserves the demand of the traveling public with ADR options in
Concourses C and D. With the addition of C1’s 24,000 square feet of ADR space within the next
five years, the Airport will still not meet current demand. Additionally, the existing passenger
hold room at Gate C3 is significantly undersized to serve current aircraft and would be expanded
to meet standard level-of-service criteria and avoid congestion on the adjacent concourse
walkways.
The C1 Building expansion includes approximately 40,000 square feet of office space, 14,000 SF
of which is for TSA on the Bridge level, and another 7,000 SF of office for use by lounge operators
The remaining 19,000 SF will be allocated to either ADR tenants, or the Port of Seattle.
The Port of Seattle has received multiple letters of interest from tenants for potential lounge
spaces in anticipation of the C1 Building Expansion project. Specific tenants for this lounge space
are in preliminary negotiations.
Furthermore, the expanded facility will include the ability to accommodate All Gender
Restrooms, Mediation Rooms and Nursing Mothers Suites.
ADDITIONAL BACKGROUND
The C1 project will be the first project that has been identified as a “Tier three project” under the
Port’s new Sustainable Project Framework; and the project team will execute design and
construction work consistent with the following Commission-approved approach:
1. Integrate sustainability early in the capital process by establishing a team of project-
specific experts through the Sustainable Project Assessment and Review Committee
(SPARC).
2. Select and apply the relevant Sustainable Evaluation Framework criteria to highlight
tradeoffs and benefits during development of the Sustainable Design Approach.