Capital (cont’d):
– Reconstructing vertical circulation
core while passengers moving
through area
• Scope Additions
Expense:
• Additional contaminated & unsuitable
soils
• Customer service provision changes
• Incorporating a more rigorous activation
effort
Factors Driving Increase
Capital:
• Design development allowance, now complete
• Code changes
• Differing site conditions discovered during
construction
• Market Conditions / Contractor Availability
– Lack of Subcontractor availability, labor
shortages, lack of qualified labor
– Ability to “pick and choose” projects
• Schedule/Phasing Complexity:
– Maintaining ‘prior to construction’ levels of
operational & customer service