COMMISSION AGENDA – Action Item No. _6e___ Page 2 of 5
Meeting Date: March 10, 2020
Template revised June 27, 2019 (Diversity in Contracting).
cost from our financial system, PeopleSoft. The ability to work between numerous systems to
obtain actual cost to date, remaining commitments (expected future invoices), and planned
future cost to project an estimated at completion (EAC) cost is especially difficult for small works
construction projects which have an aggressive schedule and restrictive project budgets, but are
faced with the same systematic lag times in having actual cost data. As internal labor costs,
department allocated overhead, vendor invoices, and P-Card transactions were being reconciled
throughout November and December, it was realized that costs had further exceeded $300,000
and were approaching $440,000.
A thorough review of lessons learned, and final scope analysis revealed that multiple mistakes
had been made on the project:
1. Marine Maintenance should have created two separate projects to appropriately capture
both the upgrades to the existing electrical service (Substation No. 5 & 8) and the
development of new Electric Vehicle Charging Stations. Although these two work projects
are related, they are distinctly two separate assets which would justify two separate work
projects and authorizations – the two systems have differing useful lives and the
substation infrastructure supports broader electrical needs at SBM. The best approach
from the onset should have been a recognition of one major works CIP of $440,000 going
for Commission authorization in July of 2018. Within this CIP, the two work projects would
capture costs of the two separate assets with differing depreciation schedules.
2. During construction Port crafts were called upon on more than one occasion to respond
to unexpected utility failures. Also, equipment failures during construction halted
operations on two occasions. Marine Maintenance did not have staffing capacity or
available equipment to maintain continuity on this project. This resulted in delays and
added overhead costs. In hindsight, this work may have been better suited for contracted
services.
3. In planning for this work in early 2018, our team underestimated the cost of the increased
project scope. This is evident in our new proposed Commission ask of $440,000 versus an
approved budget of $300,000. We are now in a difficult position of asking for
authorization on money already spent.
The above lessons learned were documented on an internal memorandum dated November 25
th
,
2019 to Maritime Managing Director Stephanie Jones-Stebbins along with recommendations for
process improvements for our team to implement in developing further transparency and
avoiding similar issues with our project delivery process moving forward.
The cost overruns noted above prevented Marine Maintenance from paying numerous
outstanding invoices to our valued equipment vendors and material suppliers. To ensure timely
payment, a retroactive work project SBM Electrical Service Upgrade (WP 106074) was created to
capture and transfer costs associated with the electrical infrastructure improvements to the
substations. A temporary amendment was also created to increase the original budget on project
SBM Electric Vehicle Charging Stations (WP 105789) to accommodate the additional costs.