COMMISSION AGENDA – Action Item No. _6c_ Page 2 of 3
Meeting Date: February 25, 2020
Template revised June 27, 2019 (Diversity in Contracting).
Aviation Project Management Group
(1) Manage the project.
(2) Procure the trailer using a Port accessible, existing state contract.
(3) Prepare design documents using an existing contract.
(4) Provide an approved building permit.
(5) Coordinate and schedule the work.
Port Construction Services
(1) Excavate and connection to existing underground site utilities (i.e., domestic water,
sanitary sewer, fire sprinkler).
(2) Provide escort services during trailer delivery and placement.
(3) Install electrical power and telecommunications utilities.
Project design was completed on July 12, the building permit was approved on August 15, and
construction started on September 12, 2019. During construction, several additional scope items
were identified whose total cost exceeded the contingencies included in the budget PCS
established.
Completing the project resulted in a project cost overrun of $25,000.
Diversity in Contracting
Not applicable to this request; all work is complete.
Scope of Work
Increase the authorization by $25,000 ($25,000 capital and $0 expense) to close out the project for
a total authorization of $575,000.
Schedule
The construction has been completed and the project is in close out.
Activity