COMMISSION AGENDA – Action Item No. _6f___ Page 2 of 6
Meeting Date: February 11, 2020
Template revised June 27, 2019 (Diversity in Contracting).
The Airport’s gate seating standard is primarily row seating and a small amount of accent
seating that provides more color options, aesthetic variety, and/or extra comfort. Older existing
seats will be relocated to airport areas in need of seating or will be removed through the Port
Asset Disposition process.
JUSTIFICATION
In a Gate Comfort Study, travelers expressed many factors that contribute to their comfort
while waiting at gates. The biggest need for improvement identified in the study was for the
provision of electrical power at seating, as well as availability of comfortable seating in the
boarding area. The installation of new seating when combined with electrical charging
capability satisfies this need. This project will replace existing older seating and offer a
consistent airport experience regardless of location. The project will provide seating that meets
the needs of people with reduced mobility.
Diversity in Contracting
This project plans to use an existing architect design services IDIQ contract which includes small
business requirements. For construction, project staff will work with the Diversity in
Contracting Department to identify a woman and minority business enterprise (WMBE)
aspirational goals.
DETAILS
Gate holdrooms will remain operational throughout the project. Construction and seating
removal and installation will occur off-hours to minimize disruptions.
The South Satellite concourse level includes a specific seating area (Relaxation Area) at the west
end for which this project will replace seating, but not include electrical charging capability. The
replacement of these seats is required due to the condition of the existing seating. The project
scope does not include replacement of seating on Concourse D or South Satellite gate
holdrooms. Work in those areas will be completed by future projects after new electrical
infrastructure is constructed to provide the necessary electrical capacity.
Scope of Work
This project will purchase and install new seating and construct electrical infrastructure as
described below:
(1) Electrical infrastructure, including new electrical panels, new conduit and wiring, and
recessed floor receptacles (approximately 20 per holdroom), on Concourse A to
provide charging capability for passengers
(2) Seating on Concourse A gate holdrooms with electrical charging
(3) Seating at The Club at SEA lounge at the South Satellite with electrical charging for
some seats re-using existing electrical circuits