COMMISSION AGENDA – Action Item No. __6g__ Page 2 of 6
Meeting Date: January 28, 2020
Template revised June 27, 2019 (Diversity in Contracting).
No additional funds are being requested as part of this action; however, a future Commission
action will be required to authorize additional funding to complete the project. The additional
budget required will not be known until redesign is complete and new estimate developed. The
overall project cost increase is also subject to a majority-in-interest (MII) vote of signatory
airlines, anticipated to occur in April 2020. Should a negative MII vote occur, the delivery of the
bollards, as well as the construction of the project, will be delayed one year per the terms of
the Airline Operating Agreement.
JUSTIFICATION
The Phase II of the TSE program is necessary, as it will provide an improved safe environment
for the airport passengers, vendors and staff. These improvements also provide ADA compliant
access improvements as recommended by the Accessibility Study completed by the Open Doors
Organization (ODO). These improvements support the port’s goal of making Seattle-Tacoma
International Airport the most accessible airport in the nation for people with disabilities.
Diversity in Contracting
Project staff worked with the Diversity in Contracting Department and have established an
eight percent women- and minority-owned business enterprise (WMBE) aspirational goal for
the construction project.
DETAILS
TSE Phase II includes the installation of bollards on the arrivals and departures curbsides and at
the entrances to each of the pedestrian skybridges and along the courtesy vehicle plaza in the
main garage. Site and structural facility constraints limit the type of crash rated bollards that
can be used, and therefore the number of potential vendors who can meet the project
requirements.
On July 23, 2019, the project was advertised for construction bids with an engineer’s estimate
in the amount of $8,568,103. A total of four bids were received, on August 28, 2019, ranging in
price from $11,660,474 to $20,697,925. The apparent low bid was withdrawn due to a
significant bid error resulting in a new apparent low bid of $14,654,750 for a total overall
project cost of $24,500,000. Port staff reviewed the bid information and determined that one
of the key differences between the engineer’s estimate and the bids was a higher cost for the
bollards. The review identified that the cost for the 443 vendor supplied bollards was $3
million, more than double the engineer’s estimate value of $1.3 million. The bid review also
clarified that all bidders were sourcing bollards from the same vendor, who likely realized they
were sole source and as a result was able to demand a higher overall cost.
With the information from the bid results, the project team determined procuring the
structural bollards separately may increase supplier competition resulting in a lower bollard
cost. Since the initial bid opening, four vendors have been identified that can provide bollards
that meet the project’s requirements; two located in the United States and the two new