Terminal 91 Berth 6 & 8
Replacement
Kenneth Lyles – Director, Fishing and Commercial Operations
Mark Longridge – Capital Project Manager
Item No.: 8b_Supp
Meeting Date: January 7, 2020
Project Location
2
Demand for Berths Increasing
3
Vessel Size Increasing
4
Current Condition
5
• 1000% of pier load restricted
• 30% of pier condemned (no vehicle traffic)
Current Condition
6
• Creosote Timber Construction
• Significant underdock and fender deterioration
Proposed Replacement
7
Initial Project Schedule
• Design Funding Authorization: Q1 2020
• Design Contract Executed:Q3 2020
• Design and Permitting Complete,
Construction Funding Authorization: Q2 2022
• Construction Contract Advertisement – Award: Q3 2022
• Construction Complete: Q3 2023
8
9
Degree of Uncertainty
Capital Improvement Plan Status & Certainty
10