COMMISSION AGENDA – Action Item No. __6p__ Page 2 of 4
Meeting Date: December 10, 2019
Template revised June 27, 2019 (Diversity in Contracting).
complete the moves of their equipment and Vanderlande took on this effort as a part of their
work, not realizing the exclusion. This exclusion became apparent during the second checkpoint
installation. To complete the installation, Vanderlande undertook this additional work. This
proposed contract change in the amount of $445,000 will pay for the remaining work to move
third-party equipment at Checkpoints 2 and 3 and the International Arrivals Facility (IAF).
Per the General Delegation of Authority, Section 4.2.3.8, Commission authorization is required
to execute a contract amendment greater than $300,000.
Schedule
Due to design challenges, electrical and data infrastructure construction contracting issues,
equipment damage, and most recently vendor equipment production issues, this project has
fallen behind schedule. The project has limited “windows” of time to complete equipment
installations and avoid peak travel periods. These issues have delayed the installation of the
remaining equipment until 2020, with an anticipated project completion of Q3 2020, which
includes the International Arrivals Facility (IAF) checkpoint installation.
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Procure a separate entity to perform the remaining third-party equipment
moves and testing for the remainder of the project
Cost Implications: $500,000
Pros:
(1) The equipment move work would be competed among potential vendors.
Cons:
(1) The pool of eligible vendors is limited by TSA contracting certification requirements.
(2) Internal costs to the project will increase for additional procurement and coordination
effort.
(3) Coordination during installation will be more difficult and risk of mis-communication
and change orders will increase.
(4) This will result in further schedule impacts to the project to acquire contract(s) with
different vendors.
This is not the recommended alternative.
Alternative 2 – Complete the change order as requested
Cost Implications: Increase to the contract of $445,000; there is no budget increase to the
project
Pros:
(1) Less overall cost and performance risk to the project having Vanderlande supply third-
party equipment moves.
(2) Schedule will not be impacted by having to contract and coordinate separately with a
third-party equipment move vendor.