COMMISSION AGENDA – Action Item No. 6f Page 2 of 5
Meeting Date: December 10, 2019
Template revised June 27, 2019 (Diversity in Contracting).
that are longer lasting, more environmentally friendly and stronger than the timber systems they
replace.
The current fender pile system at these berths consists of ammoniacal copper zinc arsenate
(ACZA) treated piles, chocks and walers in a conventional arrangement typical of timber fender
systems. While environmentally superior to traditional creosote piles used in the past, these piles
have a relatively short service life under harsh conditions. Several of the piles currently are
broken, rotted or have significant section loss around the waterline.
The designated use of these berths by industrial customers contributes to accelerated wear of
the current timber system due to chafing and abrasion of the pile faces. Providing a stronger
wear face of high density polyethylene (HDPE or similar) will also be a design priority to ensure a
long life for the new system.
All in-water work for the installation of the new piles must be completed within the permitted
fish window between August 1
st
and February 15
th
of each year, while above water work may be
completed after this time (upper bullrail work etc.). This construction window falls during some
of the busiest time for these berths, when fishing vessels are in port for refitting and
maintenance, and it is expected that operational constrains may further tighten the time the job
site is available for construction. The project team will work closely with operations staff to
minimize any impacts to both the construction and operations schedules.
Diversity in Contracting
The project team will coordinate with the Diversity in Contracting Department to determine
appropriate WMBE aspirational goals for this project.
DETAILS
Scope of Work
Overall project scope would include the replacement of approximately 1,120 linear feet of old
and deteriorated fender pile system, along with the remaining bullrail and brow at the northwest
corner of Pier 91 with a new steel fender system to facilitate vessel and barge moorage for
existing tariff and Preferential Use Agreement tenants.
Design and permitting scope under this authorization will include preparation of plans,
specifications and estimates for completing this work, and coordination of all applicable permits
required for in-water work to repair these sites.
Schedule
Permitting and operational concerns will have a significant impact on this project schedule. While
it is possible that this work might be performed under the Port’s existing programmatic permit
for maintenance and pile replacement this largely depends on the design spacing (and resultant
number) of the piles. This cannot be determined until design has begun in earnest. Also, the