COMMISSION AGENDA – Action Item No. __6d__ Page 2 of 5
Meeting Date: December 10, 2019
Template revised June 27, 2019 (Diversity in Contracting).
Based on the age of the pumps, the fourth pump will likely also begin to experience
performance problems in the near term.
Installing new isolation valves at each pump will allow individual pumps to be isolated to
facilitate and streamline required maintenance and testing. Using the current valve
arrangement any maintenance on the pump requires four pumps to be isolated from the
system.
Diversity in Contracting
The project staff, in coordination with the Diversity in Contracting department, have set a 4%
woman and minority-owned business enterprise (WMBE) aspirational goal for this Building
Engineering Systems contract. A significant portion of the project cost will be in the purchase of
the fire pump system which limits the amount of subcontracting that is available.
DETAILS
The pump house, located on air cargo road, was built in the 1970s and houses two electric
pumps to fill the reservoir, two electric pumps for baseline domestic/fire protection water, and
six pumps that support the fire emergency need. The six fire pumps are split as four diesel and
two electric pumps. As the airport grew the pump house was expanded in the early 2000s to
include four additional diesel pumps, for a total of eight diesel and two electric pumps, to
supply the peak need of 19,000 gallons per minute. The expansion added pump capacity but did
not update any of the existing pumps. This project will replace existing pumps 5 through 8, and
install additional isolation valves, so one pump can be taken off line while the others remain
operational.
The NFPA requires that emergency fire pumps be tested annually to certify the pressure and
flow rate. This project will install an inline flow meter on the fill line of the 2-million-gallon
water reservoir. The pump house piping configuration was designed so that each individual
emergency fire pump can feed the reservoir through a series of valve alignments. The inline
meter with calibrated gauges can be used to certify the pumps while filling the reservoir and
not waste any water for testing.
Scope of Work
(1) Demolish and remove four fire pump systems (pump, engine, control panel, and
associated connecting piping).
(2) Install four new equivalent fire pump systems.
(3) Provide wiring, testing, commissioning, and associated equipment for a fully
functional fire pump system.
(4) Install valves to isolate each of the new pumps for maintenance.
(5) Install a bypass line that includes a direct measurement flow meter for annual flow
testing. Provide the wiring, testing, commissioning, and associated equipment for a
fully functional flow meter system.