COMMISSION AGENDA – Action Item No. 6k Page 3 of 5
Meeting Date: November 19, 2019
Template revised June 27, 2019 (Diversity in Contracting).
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Maintain current level of security of the three remote modular buildings with key
locks at exterior doors.
Cost Implications: Negligible. A modest operating budget is maintained under the status quo for
issuing keys to new personnel for access into the three buildings.
Pros:
(1) Building security is presently maintained with locked doors, requiring personnel to
either access the buildings with keys in their possession or by summoning receptionists
to permit their entry.
(2) Costs are limited to the issuance of keys to new personnel authorized entry, or to that
of re-keying doors if required.
(3) No design is required.
Cons:
(1) During normal working hours, buildings are accessible to uninvited visitors if doors are
left open or ajar.
(2) Receptionist personnel are disrupted frequently to permit entry for authorized visitors
or personnel who do not have keys in their possession.
This is not the recommended alternative.
Alternative 2 – Evaluate each of the three buildings for their security risk to determine a
hierarchy of needs for installing badge readers. Eliminate installation of the card readers to any
building that is deemed to possess an “acceptable” risk to a security breach(es).
Cost Implications: This option could reduce the budget to the Small Jobs Capital level if one or
more of the buildings were eliminated from consideration and left to remain on keyed access. A
savings of $70,000 to $100,000 (under a $350,000 budget) could be realized by reducing the
number of buildings to two.
Pros:
(1) This alternative would permit the project to proceed as a Small Jobs Capital project and
authorized by the Executive Director under the General Delegation of Authority.
(2) The construction duration (projected to be 2.5 months) would be reduced by roughly 3
weeks.
Cons:
(1) Two of the three buildings are in highly populated areas near the terminal—thus more
susceptible to non-invited intrusions. The westside field office is in a very remote area
and much more susceptible to an intrusion when the building is sparsely occupied. All
three buildings are of equal size, occupancy, and store valuable property and sensitive
documents.
(2) Cost. The installation of three buildings under one project employs an economy of
scale. Should a third building later be considered for card readers, the cost would be
proportionally much higher (at least $150,000 or more).