COMMISSION AGENDA – Action Item No. __8d__ Page 3 of 6
Meeting Date: November 12, 2019
Template revised September 22, 2016; format updates October 19, 2016.
on the mezzanine level, would be the best alternative to reduce the shortfall. This project is
necessary to enable the utilization of these spaces.
This project was originally bid as two separate construction projects. All bids received for the
two projects exceeded the engineer’s estimate, and as a result the projects were combined and
rebid as a single construction package. The current project estimate at completion is
$21,834,000 this includes the request for $5,000,000 in this memorandum. If the original bids
would have been accepted and contracts awarded the total project cost would have been
$24,716,000. If these contracts had been awarded the project team is confident that an
authorization for additional budget would still have been required.
The project has experienced major construction change orders above and beyond the projected
costs due to business and customer service improvements, costlier than anticipated unforeseen
field conditions, and designer errors and omissions. These costs include additional barricades,
errors in elevator pit depths, added power and communications for temporary food carts,
delays in closing tenant spaces, pest mitigation, unforeseen conditions, and additional support
costs for AV Maintenance, Port Construction Services, and design.
There are currently two change orders related to these decisions that require Commission
authorization; both will extend the contract duration more than 60 days and increase the
contract value by more than $300,000. Final values are still under negotiation, and staff
estimates the additional cost and time due to changes in construction phasing of approximately
$530,000 and 120 calendar days. Impacts from unforeseen utilities are currently estimated at
$300,000 and 90 calendar days.
Scope of Work
Upgrade the infrastructure in the Central Terminal to include adding new heating, ventilation,
and air conditioning (HVAC) air handling units, variable air volume boxes, plumbing, electrical,
mechanical systems, demising walls, elevators and stairways, and demolition to prepare the
mezzanine and all Central Terminal spaces for future tenant build-out projects. This will require
closing all Central Terminal tenant spaces, in multiple phases, to accomplish the work.
Schedule
Activity