Item No. 6j supp Meeting Date: November 12, 2019 2020 Airfield Pavement Replacement Projects CIP# C800483 2020 Airfield Pavement Replacement Projects Scope The 2020 projects are comprised of the following 6 Work Areas: • Area 1: Reconstruction of the Asphalt Concrete Pavement (ACP) at Cargo 2 east laydown area. • Area 2: Reconstruction of the Portland Cement Concrete Pavement (PCCP) and ACP at the Vehicle Service Road, Cargo 2, Cargo 3, and Industrial Waste System utility upgrade. • Area 3: Reconstruction of the ACP at North Satellite taxilane shoulder and the apron south of the Airport Rescue and Fire Fighting station. • Area 4: Reconstruction of the PCCP at Taxilane W and Taxiway B at the north entrance to the South Satellite. • Area 5: Reconstruction of the PCCP at Taxilane W and Taxiway B at the south entrance to the South Satellite. • Area 6: Replacement of individual PCCP (w/ Quick-Set Panels) and Joint seal on Taxiway B. 3 Schedule • Commission Authorization for Construction • Contract Execution • In-use date 2019 Quarter 4 2020 Quarter 1 2020 Quarter 4 4 Budget • Design • Construction • Total $1,285,000 $17,131,000 $18,416,000 5 Project Risks • There are a limited the number of gate closures available airport-wide for construction. • Gate opening delays on other airport projects could delay the start of portions of the 2020 Airfield Pavement Replacement Project work. 6