2020 Airfield Pavement Replacement Projects
CIP# C800483
Item No. 6j supp
Meeting Date: November 12, 2019
2020 Airfield Pavement Replacement Projects
Scope
Area 1: Reconstruction of the Asphalt Concrete Pavement (ACP) at Cargo 2 east laydown area.
Area 2: Reconstruction of the Portland Cement Concrete Pavement (PCCP) and ACP at the Vehicle
Service Road, Cargo 2, Cargo 3, and Industrial Waste System utility upgrade.
Area 3: Reconstruction of the ACP at North Satellite taxilane shoulder and the apron south of the
Airport Rescue and Fire Fighting station.
Area 4: Reconstruction of the PCCP at Taxilane W and Taxiway B at the north entrance to the South
Satellite.
Area 5: Reconstruction of the PCCP at Taxilane W and Taxiway B at the south entrance to the South
Satellite.
Area 6: Replacement of individual PCCP (w/ Quick-Set Panels) and Joint seal on Taxiway B.
3
The 2020 projects are comprised of the following 6 Work Areas:
Schedule
Commission Authorization for Construction 2019 Quarter 4
Contract Execution 2020 Quarter 1
In-use date 2020 Quarter 4
4
Budget
Design $1,285,000
Construction $17,131,000
Total $18,416,000
5
Project Risks
There are a limited the number of gate closures available
airport-wide for construction.
Gate opening delays on other airport projects could delay the
start of portions of the 2020 Airfield Pavement Replacement
Project work.
6