Item No. 9b . Meeting Date: October 22, 2019 Maritime and Economic Development 2020-2024 Capital Improvement Plan (CIP) Sustaining the Working Waterfront October 22, 2019 1 Agenda • Capital Improvement Plan (CIP) Development Schedule • Review CIP Priorities and Project Status • Key Assumptions • Overview of 2020 to 2024 CIP - Deeper dive on key projects - Discuss new projects (not included in 2019-2023 CIP) - Five Year Estimated Spend • Discuss Next Steps - Plan of Finance • Appendix 2 2020 CIP Development 2020 CIP Planning (Spring) Preliminary 2020 CIP & Prioritization (June) 2020 MD/EDD Business Plan & Budget Development Commission Briefing CIP Development Commission Briefing (June) (Aug 13) Commission Budget Study Session 2020-2024 CIP Briefing (Oct 8) Year two of five year investment plan Tax Levy & Draft Plan of Finance Commission Briefing First Reading & Public Hearing for 2020 Budget 2nd Reading & Final Passage of 2020 Budget (Oct 22) (Nov 13) (Nov 19) 3 Working Waterfront Principles 1. Maximize the use of the Port's deep-water facilities and industrial lands to serve Maritime Industrial uses 2. Expand economic, cultural and community benefits 3. Support financial sustainability of the Port 4. Incorporate leading edge environmental stewardship 5. Facilitate improved transportation mobility of people and goods in the region 6. Provide consistent excellent customer service 4 Capital Improvement Plan Priorities Asset Stewardship: Financial Sustainability: Community and Environment: Maintaining the Port's capital assets and modernizing Seattle's working waterfront Investing in projects that support maritime industries and the Port's long term funding capacity Stewarding our environment responsibly, partnering with surrounding communities, and promoting social responsibility 5 Key Assumptions • Proposed CIP assumes continuation of five-year investment plan - Year two of 3% annual levy increase - Projects have been prioritized according to: • Alignment with Century Agenda • Contribution to Financial Sustainability, and/or • Identification as Critical Renewal & Replacement Projects - Funded CIP excludes $187M for prospective projects, of which $127M would be used for asset renewal and replacement • Expanded capital capacity resulting from new project revenues coming online, maturing bonds, and reduction of strategic reserve • Updated NWSA operating forecast not yet available • Funding capacity and taxy levy briefing scheduled for October 22 6 Degree of Uncertainty Capital Improvement Plan Status & Certainty Port historically delivers 80 percent of CIP over a five year period 7 Major Project Updates and Highlights Updates from 2019-2023 key projects • Advanced the status on 11 of the 12 major projects • Some projects have longer schedules, but all on track in the 5 year horizon Terminal 91 Uplands: Design team selected by Q4 2019 T46 Cruise Terminal: • Partner RFP submittals due October 16, with selection in Q1 2020, • Full EIS to begin scoping this month • Design of Port lead elements underway Waterfront Electrification: P66 electrification coming to Commission for design funds next month. Complete in 2022. 8 Maritime & Economic Development Proposed 2020-2024 CIP Est im Co ated mp let ion A Ste sset wa rds hip Fin a Sus ncia l tai na Env bility ir & C onm om ent mu nit y Sta tus Maritime & Economic Development 2020-2024 CIP $millions Projects included in 2019-2023 CIP: Terminal 117 Restoration Bell Harbor Conference Center Modernization Fishermen's Terminal Docks 3, 4 & 5 Fixed Pier Improvements New Cruise Facility (Assumes 50% Tenant Cost Share) Terminal 91 Uplands Development Fishermen's Terminal Gateway Building Fishermen's Terminal Maritime Innovation Center Salmon Bay Marina Docks D & E Replacement Pier 66 HVAC Systems Upgrade Terminal 91 Berth 6 & 8 Redevelopment Pier 66 Shorepower Waterfront Electrification Harbor Mooring Dolphins Small Capital/Fleet/Projects Underway MD/EDD CIP Reserve x x x x x x x x x x x - x - 5 5 5 4 4 4 4 4 4 3 3 3 Q2 2021 Q3 2020 Q2 2020 Q2 2023 Q2 2023 Q3 2022 Q3 2022 Q3 2023 Q4 2021 2022 2022 2022 $22.8 $10.4 $2.5 $98.9 $38.8 $21.8 $10.1 $8.9 $1.8 $35.0 $16.9 $4.5 $35.4 $25.0 - Total for Projects included in the 2019 - 2023 CIP Environment 15% Asset Stewardship 36% Financial Sustainability 49% $332.8 New Projects Proposed for 2020-2024 CIP: T102 Harbor Island Marina E Dock World Trade Center HVAC Replacement P66 Bell Harbor Marina Pile Wraps T46 Replace N Pier Structure T91 Northwest Fender T91 New Cruise Gangway Jack Block Park Pier Replacement New or Previously Deferred Projects Under $2 million* x x x x x x - - x - 3 3 3 2 2 2 2 2021 2021 2024 2024 2021 2022 2021 $3.9 $3.8 $3.5 $64.4 $6.6 $4.5 $2.9 $18.1 Total New Projects Proposed for 2020-2024 CIP $107.5 Total Maritime/Economic Development CIP $440.3 Chart does not include CIP Reserve/Small Projects/Projects Underway or non MD/EDD Projects Status: 1 = Prospective 2 = Pending Authorization 3 = Division Endorsed 4 = Design Authorized 5 = Construction Authorized *See slide in appendix for more information *Changes in status and estimated completion are bold 9 Changes to Estimates & Costs from 2019-2023 CIP Asset Financial Environme Maritime & Economic Development Proposed 2020- Stewardshi Sustainabili nt & Status 2018 p ty Community 2024 CIP Status Nov 2018 Completion Estimated Completion Nov 18 Cost $millions Projects included in 2019-2023 CIP: Terminal 117 Restoration x Bell Harbor Conference Center Modernization Fishermen's Terminal Docks 3, 4 & 5 Fixed Pier Improvements x x 4 5 Q2 2020 Q2 2021 $17.9 $22.8 4 5 Q3 2020 Q3 2020 $9.9 $10.4 4 5 Q1 2021 Q2 2020 $6.1 $2.5 New Cruise Facility (Assumes 50% Tenant Cost Share) 1 x 2 4 Q2 2022 Q2 2023 $100.0 $98.9 Terminal 91 Uplands Development x 3 4 Q3 2022 Q2 2023 $39.0 $38.8 Fishermen's Terminal Gateway Building x 4 4 Q3 2021 Q3 2022 $23.0 $21.8 3 4 Q3 2021 Q3 2022 $10.5 $10.1 Fishermen's Terminal Maritime Innovation Center x 1Includes electrification 2Does not include electrification 3Includes both projects under $300K and projects near completion like Shilshole Bay Marina Restrooms Salmon Bay Marina Docks D & E Replacement x 2 4 Q3 2020 Q3 2023 $5.9 $8.9 Pier 66 HVAC Systems Upgrade x 2 4 Q4 2021 Q4 2021 $2.9 $1.8 2 3 Q4 2021 2022 $35.0 $35.0 2 3 2022 2022 $30.0 $16.9 2 3 Q3 2020 2022 $3.6 $4.5 4Based on proposed CIP Reserve Policy Terminal 91 Berth 6 & 8 Redevelopment 2 x Pier 66 Shorepower Waterfront Electrification x Harbor Mooring Dolphins x Small Capital/Fleet/Projects Underway3 - - - $24.7 $35.4 MD/EDD CIP Reserve4 - - - $40.0 $25.0 $348.5 $332.8 Total for Projects included in the 2019 - 2023 CIP New Projects Proposed for 2020-2024 CIP: T102 HIM E Dock x 3 3 2021 - $3.9 WTC HVAC Replacement x 2 3 2021 - $3.8 P66 BHM Pile Wraps x 3 3 2024 - $3.5 T46 Replace N Pier Structure x 1 2 2024 - $64.4 T91 Northwest Fender x 2 2021 - $6.6 2 2 2022 - $4.5 1 2 2021 - T91 New Cruise Gangway x JBP Pier Replacement New or Previously Deferred Projects Under $2 million* x - - - $2.9 $18.1 Total New Projects Proposed for 2020-2024 CIP $107.5 Total Maritime/Economic Development CIP $440.3 Status: 1 = Prospective 2 = Pending Authorization 3 = Division Endorsed 4 = Design Authorized 5 = Construction Authorized *See slide in appendix for more information 10 Project Additions to 2020-2024 CIP 2020-2024 Cost Estimate Life/Safety Related Category Project Status T46 Replace N Pier Structure $64.4 No Asset Stewardship 2 T91 Northwest Fender $6.6 No Asset Stewardship 2 T91 New Cruise Gangway $4.5 No Financial Sustainability 2 T102 Harbor Island Marina E Dock $3.9 Yes Asset Stewardship 3 World Trade Center HVAC Replacement $3.8 No Asset Stewardship 3 P66 Bell Harbor Marina Pile Wraps $3.5 No Asset Stewardship 3 Jack Block Park Pier Replacement $2.9 Yes Asset Stewardship 2 Capital Project ($ in millions) *Only Projects >$2M shown totaling $89.6M. For full list of projects, see appendix Status: 1 = Prospective 2 = Pending Authorization 3 = Division Endorsed 4 = Design Authorized 5 = Construction Authorized 11 Location of T46 North Pier Structure North Pier of T46 on wood pilings is approximately 700ft by 100 feet 12 Five-Year Spend by Current Project Status $s in millions $200 $175.5 $180 $160 $140 $109.6 $120 $100 $80 $60 $58.4 $58.5 $38.3 $40 $20 $0 2020 2 - Pending Authorization 2021 3 - Division Endorsed 2022 4 - Design Authorized 2023 4 - Design Authorized (Cruise Terminal) 2024 5 - Construction Authorized 13 Cash Flow Adjusted Five-Year Spend Maritime and Economic Development CIP Cash Flows ($ mil.) 200 158 150 100 92 82 58 50 50 0 2020 2021 2022 2023 2024 (50) Maritime and Economic Development CIP CIP Reserve CIP Cash Flow Adjustment Estimated Adjusted Cash Flow 14 Capital Delivery Improvement Initiative • Examine all factors impacting Capital Delivery and Develop Road Map / Recommendations for improvements. • Establish: o Senior Advisory Group: Internal/External membership (ERP) o Executive Steering Group: Internal Cross Port membership o Subject Matter Working Groups o Implementation Teams • Work Areas: Contracting, Human Resources, Innovation, Sustainability, Delegation, Grants, Permitting, Safety, Coordination/Deconfliction, Estimation, Cost Control, Oversight, Portfolio Management. • Organize and Charter Workplan in 4th Quarter. 15 Summary Recommendation: Continue implementing 5 Year Investment Plan initiated in 2019. • A $440M CIP with focus in: o Financial Sustainability ‒ 49% o Asset Stewardship - 36% o Environment - 15% • Capital Plan takes into account: o o o Increased revenues Prudent Financial Management Retiring debt 16 Appendix 17 202 4 202 3 202 2 202 1 202 0 Maritime & Economic Development Proposed 2020-2024 CIP Est im Co ated mp let ion A Ste sset wa rds hip Fin a Sus ncia l tai na Env bility ir & C onm om ent mu nit y Sta tus Maritime & Economic Development 2020-2024 CIP $millions Projects included in 2019-2023 CIP: Terminal 117 Restoration Bell Harbor Conference Center Modernization Fishermen's Terminal Docks 3, 4 & 5 Fixed Pier Improvements New Cruise Facility (Assumes 50% Tenant Cost Share) Terminal 91 Uplands Development Fishermen's Terminal Gateway Building Fishermen's Terminal Maritime Innovation Center Salmon Bay Marina Docks D & E Replacement Pier 66 HVAC Systems Upgrade Terminal 91 Berth 6 & 8 Redevelopment Pier 66 Shorepower Waterfront Electrification Harbor Mooring Dolphins Small Capital/Fleet/Projects Underway MD/EDD CIP Reserve x x x x x x x x x x x - x - 5 5 5 4 4 4 4 4 4 3 3 3 Q2 2021 Q3 2020 Q2 2020 Q2 2023 Q2 2023 Q3 2022 Q3 2022 Q3 2023 Q4 2021 2022 2022 2022 - Total for Projects included in the 2019 - 2023 CIP $11.4 $10.4 $2.5 $2.8 $0.8 $1.0 $0.7 $0.1 $0.8 $0.4 $0.7 $0.1 $17.5 $3.0 $10.6 $0.0 $0.3 $0.3 $0.3 $20.0 $4.8 $10.0 $5.0 $1.0 $1.0 $10.0 $13.2 $2.6 $5.6 $3.0 $72.0 $14.0 $10.0 $4.0 $4.0 $0.0 $24.6 $3.0 $1.8 $4.7 $5.5 $4.1 $14.0 $0.8 $0.5 $3.8 $4.2 $5.5 $3.4 $8.0 $22.8 $10.4 $2.5 $98.9 $38.8 $21.8 $10.1 $8.9 $1.8 $35.0 $16.9 $4.5 $35.4 $25.0 $52.1 $86.8 $143.9 $33.2 $17.0 $332.8 $0.1 $0.7 $0.2 $0.0 $3.6 $0.0 $0.3 $1.4 $3.6 $3.1 $0.7 $3.6 $3.0 $0.5 $2.6 $5.9 $0.3 $6.3 $22.9 $5.3 New Projects Proposed for 2020-2024 CIP: T102 Harbor Island Marina E Dock World Trade Center HVAC Replacement P66 Bell Harbor Marina Pile Wraps T46 Replace N Pier Structure T91 Northwest Fender T91 New Cruise Gangway Jack Block Park Pier Replacement New or Previously Deferred Projects Under $2 million* x x x x x x - - x - 3 3 3 2 2 2 2 2021 2021 2024 2024 2021 2022 2021 Total New Projects Proposed for 2020-2024 CIP Total Maritime/Economic Development CIP $2.6 $22.0 $0.0 $25.0 $4.0 $0.0 $13.8 $3.9 $3.8 $3.5 $64.4 $6.6 $4.5 $2.9 $18.1 $2.8 $0.3 $7.6 $31.6 $25.4 $21.3 $107.5 $58.4 $109.6 $175.5 $58.5 $38.3 $440.3 Status: 1 = Prospective 2 = Pending Authorization 3 = Division Endorsed 4 = Design Authorized 5 = Construction Authorized *See slide in appendix for more information *Changes in status and estimated completion are bold 18 New or Previously Deferred Projects under $2M Project Name Fishermen's Terminal C3 Building Roof Replace Maritime Video Camera Project Salmon Bay Marina Uplands Building Shilshole Bay Marina Boat Wash Shilshole Bay Marina Dock X Pier Replacement Shilshole Bay Marina Fuel Float Rehabilitation Terminal 106 Mooring Dolphins Status 2 2 4 3 2 2 2 Total 686 1,800 1,500 954 1,670 470 100 Pier 91 West Slope Stabilization Repurpose Pier 69 datacenter space World Trade Center West Roof Replacement Pier 66 Roof Upgrades Pier 66 Anthony's Mechanical Roof Renewal 3 2 2 2 2 1,000 70 690 687 700 Central Waterfront Bridge Elevator Modernizations World Trade Center Garage Elevator Mods Pier 69 Clerestory and Skylight Replacement Salmon Bay Fire Suppression Terminal 91 Pier Stormwater Improvement Phase I Pier 66 Fender Overhaul Terminal 10 Mooring Dolphins 3 2 2 3 3 2 2 1,450 1,930 800 687 1,050 1,729 100 Total • Project costs in $000s • Only 2020 to 2024 project spending shown • Some projects have spending before or beyond five-year period • Does not include Small Capital Projects (projects < $300K in total cost) 18,073 19 Prospective Projects not currently funded in the CIP Maritime Prospective Projects $millions Economic Development Prospective Projects $millions Fishermen's Terminal NW Dock West Improvements New Marine Maintenance Shop Waterfront Electrification $41.8 $15.5 $13.0 Strategic Land Acquisition Pier 69 HVAC Components Replace Pier 69 Concrete Dock Rehabilitation $30.0 $7.6 $7.5 Terminal 91 Pier Stormwater Improvement Phase II Salmon Bay Marina Roof Replacements Shilshole Bay Marina Dry Boat Moorage Fishermen's Terminal C15 Building Roof Replacement Pier 91 Slope Stabilization Pier 66 Apron Cathodic Protect Pier 66 BHM Wavebreak Protect Terminal 91 Dredge Berth M Terminal 91 Widen West Berth Access Shilshole Bay Marina G Dock Rehabilitation Shilshole Bay Marina Esplanade Upgrades Shilshole Bay Marina W Dock Small Boat Floats $10.0 $9.0 $8.0 $5.5 $5.0 $5.0 $4.7 $4.0 $3.0 $2.7 $1.7 $1.4 Pier 69 Restrooms Remodel Pier 69 Front Windows & Doors Replacement Pier 69 Underdock Utility Replacement $2.4 $2.0 $1.7 Pier 69 Elevator Control Modernization Pier 34 Roof Replacement Pier 69 South Breezeway Metal Roof Replacement $1.0 $0.8 $0.5 Pier 69 Commission Chambers AV System $0.4 Fishermen's Terminal I-8 Building Roof Replacement Shilshole Bay Marina Comporter Pier Rehabilitation Fishermen's Terminal C15 Building Improvements $1.0 $0.9 $0.9 Total Maritime Prospective Projects Economic Development Prospective Projects $53.9 Total of $187M proposed projects not currently funded in CIP $133.0 20