Phase 2- Provide Redundancy
• Scope
– Install steam, condensate, and chilled water supply and return piping from the
Central Terminal baggage level connection point to the new valve room building
that will be in the north east corner of the north GT lot east of the D concourse
Annex sloped walkway.
• Purpose
– Provide a fully redundant loop system
– Enable any part of the airport terminal to operate Heating, Ventilation, and Air
Conditioning (HVAC) systems while being supplied from the south or north
steam, condensate, chilled water supply and return piping.
– This level of redundancy currently exists for Concourse A, B, and the South
Satellite. Completing this project will enable airport wide HVAC system
redundancy for all concourses and satellites.