COMMISSION AGENDA – Action Item No. _8e___ Page 2 of 6
Meeting Date: October 22, 2019
Template revised June 27, 2019 (Diversity in Contracting).
This authorization is for Phase 1 construction only. The project team will return to Commission
for Phase 2 construction authorization at a later date.
JUSTIFICATION
The existing steam, condensate, and chilled water supply and return piping are undersized for
current and future projected system loads. The project is required to supply adequate heating
and cooling to the Terminal building and North Satellite. The NorthSTAR Program is currently
under construction and requires the completion of this work to support the operational
readiness of Phase 2 of the NorthSTAR Program by summer 2021.
Diversity in Contracting
The project manager is working with the Diversity in Contracting Department to determine
participation opportunities and set goals for women and minority business enterprises (WMBE)
attainment.
DETAILS
The existing steam, condensate, and chilled water supply and return piping are undersized for
current and future projected system loads. The project is required to supply adequate heating
and cooling infrastructure to the Terminal building and North Satellite. The project is planned to
be implemented in two phases.
The Commission authorized the full project scope on June 28, 2016. Since this time the project
team has prioritized the approved scope into two phases. Phase 1 will provide capacity
improvements to support the Terminal building and North Satellite in support of the NorthSTAR
Program. New piping will be installed from the Central Mechanical Plant to the new valve room
located north of the Main Terminal building, and from the valve room to the existing Concourse
D Annex and North Satellite connections. Phase 2 will provide capacity improvements to
support Concourses C and D and complete the interconnected loop system making the system
fully redundant. The Phase 2 scope of work requires close coordination with the baggage
optimization program, airline baggage operations, and will require additional design analysis.
Phase 2 of this project is significantly more complex in design and construction than Phase 1
and will require much more coordination construction effort.
The scope and complexity of this project has increased significantly since it was originally
presented to Commission in 2016. The new Concourse D Annex and Baggage Optimization
projects have imposed substantial cost and schedule impacts. To accommodate the Concourse
D Annex facility, the project will need to build a new valve room. This new valve room will
displace existing facilities that must also be relocated. The technical difficulties and
complexities of working in and around assets installed by the Baggage Optimization project
were also not properly accounted for in the early construction estimate. Finally, this project has
faced costly challenges associated with maintaining full airport operations during construction.