2021 2025
Airfield Pavement and Supporting
Infrastructure Replacement Program
Item No. 6c
Meeting Date: October 22, 2019
Program Scope
2
Continue programmatic approach of replacing distressed airfield
pavement, joint sealant, and supporting infrastructure at Seattle-
Tacoma International Airport
Previous 20-years of airfield investments focused on the airfield’s
runway and connecting taxiway system
This CIP will focus on replacements of damaged, high traffic
pavements (and failing utilities beneath those pavements)
supporting aircraft access to the terminals and apron areas
Program Goals
3
Focus on airfield assets having the following criteria:
(1) significantly exceeded design life
(2) continual need for emergency repair
(3) high strategic value to airfield operations
Maximize FAA Grant Funding Entitlement & Discretionary
Minimize and plan for operational impacts by performing early
programmatic construction phasing
Minimize operational impacts by replacing utilities concurrent to
pavement replacement
Infrastructure Condition and Age:
4
Existing pavements designed for 20-year life now up to 50
years old (average 43 years)
Existing pavement thickness as thin as 14 inches (average 16
inches) compared to current design of 20 inches or more
Current aircraft size and number of operations have cracked
and damaged oldest pavements
Airfield-wide failures of aging utilities many more than 50
years old
Infrastructure Condition and Age:
5
2021 to 2025 Overall Airfield Pavement and
Supporting Infrastructure Replacement Program
6
JONIT SEAL
REPLACEMENT, TYP.
PAVEMENT REPLACEMENT,
TYP.
UTILITY
REPLACEMENT,
TYP.
2021 to 2025 Budget
7
Total CIP Estimate $156,300,000
Value of Pavement Reconstruction $114,200,000
Value of Utility Upgrades and Replacements $ 42,100,000
Estimate of FAA Grant Contributions* $ 49,400,000
*Should more FAA discretionary grant money become available for this program as
packaged, the estimate of total FAA-eligible construction costs are up to $81,000,000
2021 Project Schedule
8
Commission Authorization for Design Oct 2019
30% design Dec 2019
FAA Pre-Design Conference Jan 2020
Safety Risk Management Panel (SRMP) May 2020
Authorization for bid, award and construction Oct 2020
Advertise for Bid Nov 2020
Construction start NTP Mar 2021