Airport Dining and Retail (ADR)
Tenant Reimbursement Authorization
Commission
10/22/2019
Item No. __6b_supp
Meeting Date: October 22, 2019
Overview
Airport Dining Retail (ADR) Master Plan
Impacts of Rapid Increase in Passengers since 2014
Current and future locations of impacted ADR Tenants
Requesting Commission authorization
2
ADR Master Plan
The ADR Master Plan, developed in 2013-2014, had a number of
goals:
Increase food and beverage service pre-security
South Esplanade
Gina Marie Lindsay Arrivals Hall
Expand retail business in the Central Terminal
3
Impacts of Rapid Enplanement Growth since 2014
Enplanements have increased nearly 40%
This growth has impacted all parts of the Airport, creating a
need for facility and operational changes
long security lines affecting ability to access ADR units near checkpoints
need for increased checkpoint throughput
inadequate infrastructure
4
Current locations of impacted ADR Tenants
South Esplanade, Central Terminal and Concourse D
5
Current locations of impacted ADR Tenants
Gina Marie Lindsey Hall
6
Future locations of impacted ADR Tenants
North Satellite
7
Requesting Commission Authorization
Reimburse six tenants for costs spent to date on design of units for a
total amount not to exceed $796,000
Move tenants to comparable locations if they so choose
Amend leases as necessary
8