Airport Natural Gas Supply Procurement
September 24, 2019
Item No. 8c supp
Meeting Date: September 24, 2019
Airport Natural Gas Supply Procurement
Situation
Renewable Natural Gas (RNG) contract will not provide full
requirements
Gas supply required for both bus and boiler operations
Current supply contract expires Oct 31, 2019
2
Natural Gas Contract Authorization
Request authorization for the Executive Director to approve
the action to execute a contract for natural gas
Provides integration/alignment with eventual RNG supplier
Full requirements commodity plus transportation
2-year contract with two 1-year option years - $5M NTE
Competitively bid with reliable suppliers
3