
COMMISSION AGENDA – Action Item No. _8b_ Page 2 of 7
Meeting Date: September 10, 2019
Template revised June 27, 2019 (Diversity in Contracting).
airline operations. This has occurred with Gate C15, December 2017, being inoperable for
almost a month because of a failed, obsolete motor generator set. Another failure occurred at
Gate S12, May 2019, after a quarterly inspection found the structure to be critical; which
required the PLB shut down for a significant amount of time to make temporary repairs until
the PLB can be replaced.
Diversity in Contracting
The major works contract has a five percent aspirational goal for women- and minority-owned
business enterprise (WMBE). No specific diversity in contracting goals were originally set for
this project, however, the SWMBE achievements to date are 23.8 percent.
DETAILS
Aviation Project Management has worked in conjunction with AV Operations, AV Planning, AV
Facilities and Infrastructure, and AV Maintenance to create a prioritized list of PLBs whose age
and condition are cause for replacement or refurbishment. The additional funds will be used to
complete the replacement of nine bridges covered under CIP# C800793.
Several factors, as detailed below, have driven the increased cost to replace the PLBs and fixed
walkways:
Gate S6 failed before it was scheduled to be replaced. The expedited replacement
incurred additional costs and impacted the other PLB schedules. Other structural
modifications, seismic upgrade requirements, telecommunications upgrades, and 400
Hz aircraft power modifications resulted in design and construction changes. This PLB is
complete.
Gate S11 had a severely damaged anchor bolt for one of the foundations requiring a
new foundation. Other structural modifications, differing site conditions, utility conflicts,
and seismic upgrade requirements resulted in design and construction changes. This PLB
and fixed walkway are complete.
The foundation for Gate C15 needed to be redesigned and constructed differently with
a deeper foundation. This resulted from unknown utilities and differing site conditions.
This PLB is installed and in close-out.
The foundation for Gate C11 needs to be redesigned and constructed differently with a
deeper foundation. This resulted from unknown utilities and differing site conditions.
Gate D4 has an issue with the Pre-Conditioned Air hydronic piping not having isolation
valves that allow for the replacement of the PLB. The lack of isolation valves requires the
system to be drained and valves installed prior to bridge replacement.