
COMMISSION AGENDA – Action Item No. _3d_ Page 2 of 5
Meeting Date: July 23, 2019
Template revised September 22, 2016; format updates October 19, 2016.
The Port will negotiate a maximum allowable construction cost (MACC) with the GC/CM by
April 2020. The MACC determination, if acceptable to the Port, will be used to support a
request for construction funding approval from the Commission in April 2020, after all
necessary regulatory and legal requirements have been met. Construction would then
commence in in June 2020.
Construction of the Project is contingent on approval and finalization of a credits banking
agreement, currently anticipated in Fall 2019. Construction funding will be requested from
Commission once a banking agreement is reached and an acceptable MACC determination is
received.
JUSTIFICATION
In 2009, the Commission adopted the Lower Duwamish River Habitat Restoration Plan
(LDRHRP). The purpose of the Plan was to identify objectives and opportunities for habitat
restoration on Port-owned properties along the river while supporting water dependent and
water-related business uses. The T-117 site was identified as Site 23 in the LDRHRP. Site 25
was added to the Project with Commission approval in 2011.
In addition to regulating Superfund cleanups, CERCLA creates liability for damages to natural
resources caused by “releases of hazardous substances” into the environment. EPA administers
the remediation of Superfund sites, but is not responsible to bring NRD liability claims. That
task falls to the Natural Resource Trustees (Trustees), who are designated federal, state and
tribal government entities that have management responsibility for fish and wildlife and other
resources that may have been damaged by releases of hazardous substances at a cleanup site.
Potentially responsible parties generally reach settlement agreements with the Trustees by
making a cash payment, restoring habitat through a Trustee-approved project, or buying
“habitat credits” from a third party “bank” with an accredited restoration project. Although
Trustee approval is still pending, the number of settlement “credits” available from the Project
has been determined by the Trustees and it has been submitted for approval as a habitat
credits bank.
No funding is requested as part of this authorization since the preconstruction contract is
funded under the existing design and permitting authorization approved in June 2011. Funding
authorization for construction work will be requested after a banking agreement is executed
and an acceptable MACC determination is received.
Diversity in Contracting
The project team is working with the Diversity in Contracting Department and Central
Procurement Office to include the WMBE aspiration goal into the solicitation and will include an
inclusion plan in the selection process.