AVIATION CAPITAL PLANNING &
PRELIMINARY DESIGN ACTION ITEM
July 23, 2019
Item No. ____ _3c ___
Meeting Date: July 23, 2019
Briefing overview
Project Planning Process
Near-Term Projects
Projects Requiring Preliminary Design
Glideslope Antenna Relocation
Next Steps
1
2
Project Planning Process
Master planning
- complete
Campus wide, comprehensive planning
Alternatives analysis for major plan elements
Advanced planning
- in progress
More detailed planning in focus areas of long-range plan and existing facilities
Alternatives analysis within individual projects (e.g. options for configuring curbs
and functional areas for Second Terminal)
Preliminary design
- current capital funds request
Program development for individual projects
Adequate detail required to transition projects to design
Results in a Project Definition Document (PDD)
Near-Term Projects
3
Near-Term Projects
4
Design/construction period estimates for major projects
NOTE: Preliminary design precedes design phase shown above and is not depicted.
Commission authorization is required to proceed into design
5
1) Westside Maintenance Campus
2) Aircraft Rescue and Fire-
Fighting (ARFF) Relocation
3) Roadway Improvements
4) Taxiway A/B Extension
5) Main Terminal North GT Lot
Projects Requiring Preliminary Design
1
2
4
5
3
Design/construction period estimates
6
Glideslope Antenna Relocation
Taxiway A/B project requires relocation of Runway 34R glideslope antenna
Opportunity to adjust slope angle and increase aircraft elevation on approach
Sea-Tac Stakeholder Advisory Round Table (StART) recommendation
Relocate to potentially permanent location (i.e. consistent with Taxiway A/B project)
Attempt to obtain a 3.1˚ glideslope angle
Look for ways to expedite the project
Begin design (design at risk prior to conclusion of environmental review)
Initiate procedure development as soon as possible
Design/construction by FAA with reimbursement by the Port
7
Next Steps
Following Commission authorization
Utilize $10M capital funds to conduct preliminary design
Projects currently identified as requiring preliminary design in the short term
Westside Maintenance Campus
Air Rescue and Fire-Fighting (ARFF) Facility
Taxiway A/B Extension
Main Terminal North GT Lot
North Airport Expressway Improvements
Other projects to be identified through additional advanced planning
Procure and execute professional services contracts
Enter into Reimbursable Agreements with FAA
(Glideslope)