Request Commission authorization for the Executive Director to:
1. Increase the authorized funds for the Electric Utility Supervisory Control and
Data Acquisition (SCADA) project in the amount of $10,350,000
2. Advertise and award a major works construction contract at Seattle-Tacoma
International Airport
3. Use Port crews and small works contracts to assist with the project.
• Total estimated project cost is $11,950,000, an increase of $2,300,000
• Project presented to partner airlines on June 27, 2019
– Favorably received
– Majority in Interest (MII) approval expected in August
2