
Checked Baggage Optimization Project- Phase I
March 2017 – June 2019
EXECUTIVE SUMMARY
In collaboration with Talson Solutions, LLC, an independent construction auditing firm with experience in
baggage handling systems, Internal Audit completed an audit of the Checked Baggage Optimization Project
– Phase I (Project) for the period March 2017 through June 2019. The audit was performed to assess the
quality of the Port’s monitoring of the Project to assure it was meeting project management standards.
Overall, the Port’s project team is managing the Project well and has gone through additional efforts to steer
the project completion as close as possible to the contractual substantial completion and overall Phase I
completion date. Without this effort, Phase I would be further behind the original schedule than the currently
projected four to six months. Without continuous oversight from Port staff, the project could incur additional
schedule delays.
Our review noted that Port management’s monitoring and documentation of change management aligned
with industry standards and best management practices. This was especially evident in the areas of
documenting the reasons for changes, estimating change values, complying with contractual mark-up
provisions, assessing and implementing lessons learned, and using detailed subcontractor hourly wage rates
for support of labor costs. Furthermore, the project team closely monitored PCL Construction Services, Inc.
(PCL) deficiencies in oversight of its subcontractors and expressed those deficiencies through numerous
serial letters of deficient performance. We noted that Force Account Change Orders have not been reconciled
as required and should be prior to final payment to PCL.
PCL experienced significant challenges in maintaining staff with baggage handling project experience, which
may have resulted in lack of sufficient oversight and unanticipated, less than average subcontractor
performance and delays. Furthermore, PCL’s addition of the current project manager was not facilitated by a
formal submission to the Port as required by the contract’s specifications. Other than these noted concerns,
PCL is generally meeting its contractual obligations and responsibilities. PCL’s initial schedule appeared
appropriate to meet the contractual substantial completion and overall Phase I completion dates.
We noted the following issue for managements’ consideration upon completion of Phase I:
1. (Medium) – PCL did not effectively monitor its subcontractor’s performance. As a result, critical
milestones were not met by agreed upon target dates, negatively impacting the completion dates for
Phase I.
This issue is discussed in more detail beginning on page seven of this report.
Glenn Fernandes, CPA Kenneth Brzozowski, CCA, CCP
Director, Internal Audit Talson Solutions, Engagement Director
RESPONSIBLE MANAGEMENT TEAM
Ralph Graves, Sr. Director Capital Development
Jeffrey Brown, Director Aviation Facilities & Capital Programs
Wendy Reiter, Director Aviation Security
Wayne Grotheer, Director Aviation PMG
Janice Zahn, Assistant Engineering Director, Construction