
Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
DATE: June 12, 2019
TO: Stephen P. Metruck, Executive Director
FROM: John Hall, Marine Maintenance Project Manager III
Shannon Zink, Real Estate Manager
SUBJECT: Pier 66 HVAC Controls Replacement (CIP #C801006)
Total estimated project cost:
ACTION REQUESTED
Request a single Commission authorization for the Executive Director to: (1) complete design
and construction of Phase II of the modernization of HVAC controls at the Bell Harbor
International Conference Center at Pier 66 in an amount not to exceed $450,000 of a total
estimated project cost of $750,000; and (2) use port crews to complete the work.
EXECUTIVE SUMMARY
Approval of this request will allow completion of the final phase of updating the 24-year-old
HVAC control system at Pier 66. Currently, there are two control systems in operation — the
legacy system, which controls pre-existing equipment and was installed in 1995, and the new
stand-alone digital controls (SDC) system, which is an updated operating system installed during
the recent cruise terminal build out. While the newer system is able to interact with both the
new and original controls, the legacy system is only able to work with the original controls.
In May of this year, Phase I of the modernization of the legacy controls was completed as a
small project in response to a control system failure determined to be extremely urgent. This
current request is for funding Phase II of the project to modernize the remaining legacy
controls.
JUSTIFICATION
The legacy control system, which controls critical heating and cooling equipment, is obsolete
and vendors are no longer able to obtain replacement control boards. If the remaining
outdated controls fail, we will not be able to operate the affected heating and cooling
equipment servicing the facility. In addition to minimizing disruptions of building operations,
modernized controls will improve building energy efficiencies, assist in developing a