Motion 2019-03 – On-Demand/For-Hire Ground Transportation Pilot Program Page 3 of 4
(10) There shall be quarterly outreach to owners and drivers for feedback and input on
the pilot program.
(11) The curbside manager will track and maintain records of the following:
(a) Wait time sampling of vehicle pick-ups
(b) Number of accessible trips and wait times
(c) Number of trips per operator
(d) Complaints lodged against operators and disposition
(e) Passenger service comments
(12) The Executive Director shall report to the commission on the operation of the pilot
program, including customer service and provision of accessible services, outreach
to people with disabilities and the general public, and any recommendations for
revisions, in one year from adoption of this motion.
(13) To improve accessible services, the port will develop a plan for wheelchair-accessible
transportation services at the airport to increase awareness and use of the on-
demand fleet and conduct research on potential improvements of accessible
transportation services to and from the airport, including collection of data on pre-
arranged airport transportation services.
(14) The commission directs the Port of Seattle Executive Director to engage with the on-
demand taxi/flat-rate for-hire owner and operator community at Seattle-Tacoma
International Airport to develop an agreement or memorandum of understanding
that will recognize a voluntary organization with at least five years of experience as a
not-for-profit organization operating in the state of Washington, that has an
established process for worker involvement in decision making, and that can
demonstrate support of at least 60 percent of operators included in the pilot
project.
(15) The voluntary organization and the port, along with other interested drivers and
owners, will explore the development of a process, available to all drivers and
owners, for input on the pilot program on items such as performance of the permit
relationship between the port, its curbside manager, and the owner/driver
community, including scheduling, compliance, dispute resolution, and other issues
related to management of the system.
STATEMENT IN SUPPORT OF THE MOTION
The port has extensively researched options for on-demand systems at the airport. The port
conducted and participated in three major multi-year, consultant-supported ground
transportation studies from 2015-2018 (Leigh Fisher – 2015, Transportation Research Board –
2015, Ricondo – 2017/2018). The Leigh Fisher and Ricondo work were supported by significant