Interim Westside Fire Station
Alternative Contracting
Item No. 8d_ supp
Meeting Date: May 28, 2019
Interim Westside Fire Station
Overview of intent and previous authorization (Feb 2018)
Provide Westside Fire Fighters an acceptable operating environment as soon as possible.
Modular crew quarters (5 Fire Fighters), and pre-engineered apparatus bay (2 ARFF vehicles)
proposed for speed, cost and re-usability Budget: $5.5M
Q3 2018 Complexity of design with location and utilities causing design delays and budget concerns
Value Engineering/Scope Reduction initiated
Q4 2018 Constructability Review initiated
Construction schedule and modular delivery/install intensely reviewed - Contractor information
session
Site constraints and FAA regulations burdensome
Q1 2019 Conclusion: Modulars could not be implemented within authorized budget and schedule
2
Interim Westside Fire Station Location
3
NORTH
Fire Station Location
Fire Station Site
4
Fire Station
Crew Quarters
Fire Station
Truck Shelter
Lessons Learned
Rushed project: take more time to plan and fully understand constraints, then design
Pick your building type to respond to all site issues, not just one: modular solves re-use, complicates
noise and construction (delivery)
Broaden your project partners: use the right expertise for the area: now engaged with Airfield
partners
More fully involve the end users: Fire Fighters engaged in design-build requirements development
and selection process
5
Design Build Option Developed
Pros:
Flexibility in design and construction allows for budget efficiency
Fire Fighters integrated in development of requirements and proposer evaluations
Combined single structure
Ability to refine scope to budget
Early understanding of marketplace
Cons:
Lengthened schedule Fire Fighters agree w/timing: “Build it right the first time.
Less ability to change design Fire Fighters involved in basis of design requirements from the start
No plan for re-usability
Marketplace may tell us something different than we want
6