COMMISSION AGENDA – Action Item No. _6d_ Page 5 of 5
Meeting Date: May 28, 2019
Template revised September 22, 2016; format updates October 19, 2016.
employee security screening project in the Terminal and transferred for utilization by the Phase 2
employee security screening program (C800984) at the exterior gates. At this time, a 15%-level of
design has been completed and the Employee Security Screening Phase 2 project estimate is
$7,900,000. The budget increase in the amount of $7,350,000 will be transferred from the
Aeronautical Allowance CIP (C800753) resulting in no net change to the Aviation capital budget. The
funding source will be the Airport Development Fund and future revenue bonds.
Financial Analysis and Summary
Project cost for analysis
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase
Future Revenues and Expenses (Total cost of ownership)
This project will have impacts on Aviation Maintenance operating and maintenance (AVM
O&M) costs, but to what extent is unknown at this time. Impacts will be related to the
mechanical systems for cooling of the screening rooms, electronic systems, Electronic
Technicians for the duress, cameras, access controls, and the under the vehicle inspection
equipment (outside contracted service agreement or done in-house). The full impacts on AVM
O&M can be better evaluated during the design phase of this project.
Operational staff resources are estimated at 19 FTEs for represented full employee screeners
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
November 28, 2017 – The Commission authorized advertisement and execution of a major
public works contract, procurement of additional security equipment and use of Port
forces for Phase 1 of employee security screening in the terminal.
March 28, 2017 – The Commission authorized design for a third screening room, purchase
of security equipment and the use of Port forces to complete the build out of three
employee screening rooms for Phase 1 of employee security screening in the terminal.
September 13, 2016 – The Commission authorized the purchase of equipment and buildout
of space for future security for Phase 1 of employee security screening in the terminal.